Changes
Not comparable
Paragraphs
+1 405 added · −189 removed · 6 changed
More facts (2)
Title (from)
on the proposal for a regulation of the European Parliament and of the Council on the internal markets for renewable and natural gases and for hydrogen (recast)
Title (to)
on the proposal for a regulation of the European Parliament and of the Council on the internal markets for renewable and natural gases and for hydrogen (recast)

These two texts have too little in common to be compared paragraph by paragraph (under 15 % of their paragraphs match): they are different documents rather than versions of one — for example a group’s motion and the joint text that was adopted.

Every difference

The full paragraph comparison, packaging included; long runs of unchanged paragraphs are folded. One part of the text per page.

Part 14 of 30: Paragraphs 781–840

Added10a. Within three months of the date of receipt of a network code, ACER shall provide a reasoned opinion to the ENTSOG&H or the EU DSO, as appropriate.

Added10b. The ENTSOG&H shall amend the network code in light of the opinion of ACER and re-submit it to ACER.

Added11. ACER shall revise the re-submitted network code to ensure that it complies with the relevant framework guidelines and contributes to market integration, non-discrimination, effective competition, and the efficient functioning of the market and, shall submit the revised network code to the Commission within six months of receipt of the proposal. In the revised network code, ACER shall take into account the views provided by all involved parties during the drafting of the proposal led by the ENTSOG&H and shall consult the relevant stakeholders on the revised version to be submitted to the Commission.

Added12. Where the ENTSOG&H has failed to develop a network code within the period set by the Commission under paragraph 9, the Commission may request ACER to prepare a draft network code on the basis of the relevant framework guideline. ACER may launch a further consultation in the course of preparing a draft network code under this paragraph. ACER shall submit a draft network code prepared under this paragraph to the Commission and may recommend that it be adopted.

Added13. Where the ENTSOG&H has failed to develop a network code, or ACER has failed to develop a draft network code as referred to in paragraph 12, the Commission may adopt, on its own initiative, or upon the proposal of ACER under paragraph 11, one or more network codes in the areas listed in paragraphs 1 and 2.

Added14. Where the Commission proposes to adopt a network code on its own initiative, it shall consult ACER, the ENTSOG&H and all relevant stakeholders in regard to the draft network code during a period of no less than two months.

Added15. This Article shall be without prejudice to the Commission's right to adopt and amend the guidelines as laid down in Article 56. It shall be without prejudice to the possibility for the ENTSOG&H to develop non-binding guidance in the areas set out in paragraphs 1 and 2 where such guidance does not relate to areas covered by a request addressed to the ENTSOG&H by the Commission. The ENTSOG&H shall submit any such guidance to ACER for an opinion and shall duly take that opinion into account.

Added1. The Commission is empowered to amend the network codes within the areas listed in Article 53 (1) and (2) and in Article 54(1) and (2) in accordance with the relevant procedure set out in those Articles.

Added2. Persons who are likely to have an interest in any network code adopted under Article 52 to 55, including the ENTSOG&H the EU DSO entity, regulatory authorities, transmission system operators, distribution system operators, system users and consumers, may propose draft amendments to that network code to ACER. ACER may also propose amendments on its own initiative.

Added3. ACER may make reasoned proposals to the Commission for amendments, explaining how such proposals are consistent with the objectives of the network codes set out in Article 52 of this Regulation. Where it considers an amendment proposal to be admissible and where it proposes amendments on its own initiative, ACER shall consult all stakeholders in accordance with Article 14 of Regulation (EU) 2019/942.

Added1. The Commission is empowered to adopt binding guidelines in the areas listed in this Article.

Added2. The Commission is empowered to adopt guidelines in the areas where such acts could also be developed under the network code procedure pursuant to Article 53 and 54. Those guidelines shall be adopted in the form of delegated or implementing acts, depending on the relevant empowerment provided for in this Regulation.

Added3. The Commission is empowered to adopt delegated acts in accordance with Article 63 supplementing this Regulation with regard to the establishment of guidelines in the following areas:

Added(a) details of third-party access services, including the character, duration and other requirements of those services, in accordance with Articles 5 to 7;

Added(b) details of the principles underlying capacity-allocation mechanisms and on the application of congestion-management procedures in the event of contractual congestion, in accordance with Articles 9 and 10;

Added(c) details of the provision of information, definition of the technical information necessary for network users to gain effective access to the system and the definition of all relevant points for transparency requirements, including the information to be published at all relevant points and the time schedule for the publication of that information, in accordance with Articles 30 and 31;

Added(d) details of tariff methodology related to cross-border trade of natural gas, in accordance with Articles 15 and 16 of this Regulation;

Added(e) details relating to the areas listed in Article 23(6).

Added4. The Commission is empowered to adopt delegated acts in accordance with Article 63 in order to amend the guidelines laid down in Annex I to this Regulation.

Added5. When adopting or amending guidelines, the Commission shall consult ACER, the ENTSOG&H, the EU DSO entity and, where relevant, other stakeholders.

AddedThis Regulation shall be without prejudice to the rights of Member States to maintain or introduce measures that contain more detailed provisions than those set out in this Regulation, in the guidelines referred to in Article 56 or in the network codes referred to in Article 52 to 55, provided that those measures are compatible with Union law.

Added1. Member States and the regulatory authorities shall, on request, provide the Commission with the information necessary for the purposes of enforcing this Regulation, including the guidelines and the network codes adopted under this Regulation.

Added2. The Commission shall set a reasonable time limit within which the information is to be provided, taking into account the complexity and urgency of the information required.

Added3. If the Member State or the regulatory authority concerned does not provide the information within the time limit set by the Commission, the Commission may request all the information necessary for the purpose of enforcing this Regulation directly from the undertakings concerned.

AddedWhen sending a request for information to an undertaking, the Commission shall, at the same time, forward a copy of the request to the regulatory authorities of the Member State in whose territory the seat of the undertaking is situated.

Added4. In its request for information, the Commission shall state the legal basis of the request, the time limit within which the information is to be provided, the purpose of the request, and the penalties provided for in Article 59(2) for supplying incorrect, incomplete or misleading information.

Added5. The owners of the undertakings or their representatives and, in the case of legal persons, the natural persons authorised to represent the undertaking by law or by their instrument of incorporation, shall supply the information requested. Where lawyers are authorised to supply the information on behalf of their client, the client shall remain fully responsible in the event that the information supplied is incomplete, incorrect or misleading.

Added6. Where an undertaking does not provide the information requested within the time limit set by the Commission or supplies incomplete information, the Commission may by decision require the information to be provided. That decision shall specify what information is required and set an appropriate time limit within which it is to be supplied. It shall indicate the penalties provided for in Article 59(2). It shall also indicate the right to have the decision reviewed by the Court of Justice of the European Union.

AddedThe Commission shall, at the same time, send a copy of its decision to the regulatory authorities of the Member State within the territory of which the person is resident or the seat of the undertaking is situated.

Added7. The information referred to in paragraphs 1 and 2 shall be used only for the purposes of enforcing this Regulation.

AddedThe Commission shall not disclose information acquired pursuant to this Regulation where that information is covered by the obligation of professional secrecy.

Added1. Member States shall lay down the rules on penalties applicable to infringements of this Regulation, the network codes and guidelines adopted pursuant to Articles 52 to 56 and the guidelines laid down in Annex I of this Regulation and shall take all measures necessary to ensure that they are implemented. The penalties provided for shall be effective, proportionate and dissuasive. Member States shall, without delay, notify the Commission of those rules and of those measures and shall notify it without delay of any subsequent amendment affecting them.

Added2. The Commission may, by decision, impose on undertakings fines not exceeding 1 % of the total turnover in the preceding business year where, intentionally or negligently, those undertakings supply incorrect, incomplete or misleading information in response to a request made pursuant to Article 58(4) or fail to supply information within the time-limit set in a decision adopted pursuant to Article 58(6), first subparagraph. In setting the amount of a fine, the Commission shall have regard to the gravity of the failure to comply with the requirements referred to in paragraph 1 of this Article.

Added3. The penalties provided for pursuant to paragraph 1 and any decisions taken pursuant to paragraph 2 shall not be of a criminal law nature.

AddedFinal provisions

Added1. Major new natural gas infrastructure, that is to say interconnectors, LNG and storage facilities, may, upon request, be exempted, for a defined period of time, from the provisions of this Regulation as well as from Articles, 28, 27(1), 29, 54 and Article 72(7), (9) and 73(1) of [recast Gas Directive]. Major new hydrogen infrastructure, that is to say interconnectors, hydrogen terminals and underground hydrogen storage may, upon request, be exempted, for a defined period of time, from the provisions of Articles 62, 31, 32, 33 of [recast Gas Directive] and Article 15 of this Regulation. Any such exemption shall be subject to all of the following conditions ▌:

Added(a) the investment enhances competition in gas supply or hydrogen supply and enhance security of supply;

Added(b) the investment contributes to the achievement of the Union’s climate and energy targets;

Added(c) the level of risk attached to the investment is such that the investment would not take place unless an exemption was granted;

Added(ca) demand-side solutions that do not require new infrastructure investments have been taken into account as possible alternative solutions to the new infrastructure;

Added(d) the infrastructure is owned by a natural or legal person which is separate at least in terms of its legal form from the system operators in whose systems that infrastructure will be built;

Added(e) charges are levied on users of that infrastructure; ▌

Added(f) the exemption is not detrimental to competition in the relevant markets which are likely to be affected by the investment, to the effective functioning of the internal and integrated market in energy, including gas, electricity, hydrogen and demand-side solutions, to the efficient functioning of the regulated systems concerned, to decarbonisation or to security of supply in the Union;

Added(fa) the infrastructure has not received Union financial assistance for works under Regulation (EU) 2021/1153 of the European Parliament and of the Council;

Added(fb) the exemption promotes the energy efficiency first principle and energy system integration and does not lead to the stranding of assets.

AddedThese conditions should be assessed taking into account the principle of energy solidarity. National authorities should take into account the situation in other affected Member State and balance possible negative effects with the beneficial effects on its territory.

Added2. The exemption in paragraph 1 shall also apply to significant increases of capacity in existing infrastructure and to modifications of such infrastructure which enable the development of new sources of renewable gas and low-carbon gas supply.

Added3. The regulatory authority may, on a case-by-case basis, decide on the exemption referred to in paragraphs 1 and 2.

AddedBefore the adoption of the decision on the exemption, the regulatory authority, or where appropriate another competent authority of that Member State, shall consult:

Added(a) the regulatory authorities of the Member States the markets of which are likely to be affected by the new infrastructure; and

Added(b) the relevant authorities of the third countries, where the infrastructure in question is connected with the Union network under the jurisdiction of a Member State, and originates from or ends in one or more third countries.

AddedWhere the third-country authorities consulted do not respond to the consultation or do not provide grounds for the exemption in their response within a reasonable time frame or within a set deadline not exceeding three months, the regulatory authority concerned may adopt the necessary decision.

Added4. Where the infrastructure in question is located in the territory of more than one Member State, ACER may submit an advisory opinion to the regulatory authorities of the Member States concerned within two months from the date on which the request for exemption was received by the last of those regulatory authorities. That opinion may be used as a basis for their decision.

AddedWhere all the regulatory authorities concerned agree on the request for exemption within six months of the date on which it was received by the last of the regulatory authorities, they shall inform the ACER of their decision. Where the infrastructure concerned is a transmission line between a Member State and a third country, the regulatory authority, or where appropriate another competent authority of the Member State where the first interconnection point with the Member States' network is located, may consult before the adoption of the decision on the exemption the relevant authority of that third country with a view to ensuring, as regards the infrastructure concerned, that this Regulation is applied consistently in the territory and, where applicable, in the territorial sea of that Member State. Where the third country authority consulted does not respond to the consultation within a reasonable time or within a set deadline not exceeding three months, the regulatory authority concerned may adopt the necessary decision.

AddedACER shall exercise the tasks conferred on the regulatory authorities of the Member States concerned by this Article:

Added(a) where all regulatory authorities concerned have not been able to reach an agreement within a period of six months from the date on which the request for exemption was received by the last of those regulatory authorities; or

Added(b) upon a joint request from the regulatory authorities concerned.

AddedAll regulatory authorities concerned may, jointly, request that the period referred to in the third subparagraph, point (a), is extended by up to three months.

Added5. Before taking a decision, the ACER shall consult the relevant regulatory authorities and the applicants.

Added6. An exemption may cover all or part of the capacity of the new infrastructure, or of the existing infrastructure with significantly increased capacity.

Sources & citation

Where the facts on this page come from, and how to cite it.

Data source
Licensed CC BY 4.0.
Retrieved
30 September 2026

Cite as

European Parliament (2023). “Changes between ITRE-PR-734108 and A-9-2023-0032”. Text, 16 February 2023. from ITRE-PR-734108, to A-9-2023-0032. EU Parl Watch Research. https://news.eu-parl.st-solutions.dev/texts/ITRE-PR-734108/compare/A-9-2023-0032?all=1&part=14 (retrieved 30 September 2026). Data: European Parliament Open Data, https://data.europarl.europa.eu/ (CC BY 4.0).
BibTeX
@misc{epw-text-2023-02-16,
  author = {{European Parliament}},
  title = {{Changes between ITRE-PR-734108 and A-9-2023-0032}},
  year = {2023},
  date = {2023-02-16},
  howpublished = {\url{https://news.eu-parl.st-solutions.dev/texts/ITRE-PR-734108/compare/A-9-2023-0032?all=1&part=14}},
  url = {https://news.eu-parl.st-solutions.dev/texts/ITRE-PR-734108/compare/A-9-2023-0032?all=1&part=14},
  urldate = {2026-09-30},
  publisher = {EU Parl Watch Research},
  note = {Text. from ITRE-PR-734108, to A-9-2023-0032. Data: European Parliament Open Data (CC BY 4.0)}
}