Text · Amendment list
Proposal for a Regulation of the European Parliament and of the Council establishing a framework of measures for the acceleration of industrial capacity and decarbonisation in strategic sectors and amending Regulations (EU) 2018/1724, (EU) 2024/1735 and (EU) 2024/3110
Full title
Proposal for a Regulation of the European Parliament and of the Council establishing a framework of measures for the acceleration of industrial capacity and decarbonisation in strategic sectors and amending Regulations (EU) 2018/1724, (EU) 2024/1735 and (EU) 2024/3110
Document CJ80-AM-796440 · COM(2026)0100 – C100067/2026 – 2026/0068(COD)
- Kind
- Amendment list CJ80-AM-796440
- Date
- 19 October 2026
- Committee
- Committee on International Trade Committee on Industry, Research and Energy Committee on the Internal Market and Consumer Protection
- Dossier
- 2026-0068
More facts (2)
- Formats
- Official page PDF Word
- Reference
- COM(2026)0100 – C100067/2026 – 2026/0068(COD)
Text
The text as parsed from the official Word file. Every paragraph has a link (¶) and can be saved to a project as a passage.
Jump to an amendment (269)
- Amendment 1245
- Amendment 1246
- Amendment 1247
- Amendment 1248
- Amendment 1249
- Amendment 1250
- Amendment 1251
- Amendment 1252
- Amendment 1253
- Amendment 1254
- Amendment 1255
- Amendment 1256
- Amendment 1257
- Amendment 1258
- Amendment 1259
- Amendment 1260
- Amendment 1261
- Amendment 1262
- Amendment 1263
- Amendment 1264
- Amendment 1265
- Amendment 1266
- Amendment 1267
- Amendment 1268
- Amendment 1269
- Amendment 1270
- Amendment 1271
- Amendment 1272
- Amendment 1273
- Amendment 1274
- Amendment 1275
- Amendment 1276
- Amendment 1277
- Amendment 1278
- Amendment 1279
- Amendment 1280
- Amendment 1281
- Amendment 1282
- Amendment 1283
- Amendment 1284
- Amendment 1285
- Amendment 1286
- Amendment 1287
- Amendment 1288
- Amendment 1289
- Amendment 1290
- Amendment 1291
- Amendment 1292
- Amendment 1293
- Amendment 1294
- Amendment 1295
- Amendment 1296
- Amendment 1297
- Amendment 1298
- Amendment 1299
- Amendment 1300
- Amendment 1301
- Amendment 1302
- Amendment 1303
- Amendment 1304
- Amendment 1305
- Amendment 1306
- Amendment 1307
- Amendment 1308
- Amendment 1309
- Amendment 1310
- Amendment 1311
- Amendment 1312
- Amendment 1313
- Amendment 1314
- Amendment 1315
- Amendment 1316
- Amendment 1317
- Amendment 1318
- Amendment 1319
- Amendment 1320
- Amendment 1321
- Amendment 1322
- Amendment 1323
- Amendment 1324
- Amendment 1325
- Amendment 1326
- Amendment 1327
- Amendment 1328
- Amendment 1329
- Amendment 1330
- Amendment 1331
- Amendment 1332
- Amendment 1333
- Amendment 1334
- Amendment 1335
- Amendment 1336
- Amendment 1337
- Amendment 1338
- Amendment 1339
- Amendment 1340
- Amendment 1341
- Amendment 1342
- Amendment 1343
- Amendment 1344
- Amendment 1345
- Amendment 1346
- Amendment 1347
- Amendment 1348
- Amendment 1349
- Amendment 1350
- Amendment 1351
- Amendment 1352
- Amendment 1353
- Amendment 1354
- Amendment 1355
- Amendment 1356
- Amendment 1357
- Amendment 1358
- Amendment 1359
- Amendment 1360
- Amendment 1361
- Amendment 1362
- Amendment 1363
- Amendment 1364
- Amendment 1365
- Amendment 1366
- Amendment 1367
- Amendment 1368
- Amendment 1369
- Amendment 1370
- Amendment 1371
- Amendment 1372
- Amendment 1373
- Amendment 1374
- Amendment 1375
- Amendment 1376
- Amendment 1377
- Amendment 1378
- Amendment 1379
- Amendment 1380
- Amendment 1381
- Amendment 1382
- Amendment 1383
- Amendment 1384
- Amendment 1385
- Amendment 1386
- Amendment 1387
- Amendment 1388
- Amendment 1389
- Amendment 1390
- Amendment 1391
- Amendment 1392
- Amendment 1393
- Amendment 1394
- Amendment 1395
- Amendment 1396
- Amendment 1397
- Amendment 1398
- Amendment 1399
- Amendment 1400
- Amendment 1401
- Amendment 1402
- Amendment 1403
- Amendment 1404
- Amendment 1405
- Amendment 1406
- Amendment 1407
- Amendment 1408
- Amendment 1409
- Amendment 1410
- Amendment 1411
- Amendment 1412
- Amendment 1413
- Amendment 1414
- Amendment 1415
- Amendment 1416
- Amendment 1417
- Amendment 1418
- Amendment 1419
- Amendment 1420
- Amendment 1421
- Amendment 1422
- Amendment 1423
- Amendment 1424
- Amendment 1425
- Amendment 1426
- Amendment 1427
- Amendment 1428
- Amendment 1429
- Amendment 1430
- Amendment 1431
- Amendment 1432
- Amendment 1433
- Amendment 1434
- Amendment 1435
- Amendment 1436
- Amendment 1437
- Amendment 1438
- Amendment 1439
- Amendment 1440
- Amendment 1441
- Amendment 1442
- Amendment 1443
- Amendment 1444
- Amendment 1445
- Amendment 1446
- Amendment 1447
- Amendment 1448
- Amendment 1449
- Amendment 1450
- Amendment 1451
- Amendment 1452
- Amendment 1453
- Amendment 1454
- Amendment 1455
- Amendment 1456
- Amendment 1457
- Amendment 1458
- Amendment 1459
- Amendment 1460
- Amendment 1461
- Amendment 1462
- Amendment 1463
- Amendment 1464
- Amendment 1465
- Amendment 1466
- Amendment 1467
- Amendment 1468
- Amendment 1469
- Amendment 1470
- Amendment 1471
- Amendment 1472
- Amendment 1473
- Amendment 1474
- Amendment 1475
- Amendment 1476
- Amendment 1477
- Amendment 1478
- Amendment 1479
- Amendment 1480
- Amendment 1481
- Amendment 1482
- Amendment 1483
- Amendment 1484
- Amendment 1485
- Amendment 1486
- Amendment 1487
- Amendment 1488
- Amendment 1489
- Amendment 1490
- Amendment 1491
- Amendment 1492
- Amendment 1493
- Amendment 1494
- Amendment 1495
- Amendment 1496
- Amendment 1497
- Amendment 1498
- Amendment 1499
- Amendment 1500
- Amendment 1501
- Amendment 1502
- Amendment 1503
- Amendment 1504
- Amendment 1505
- Amendment 1506
- Amendment 1507
- Amendment 1508
- Amendment 1509
- Amendment 1510
- Amendment 1511
- Amendment 1512
- Amendment 1513
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Dan Barna, Yvan Verougstraete, Elisabetta Gualmini, Anna-Maja Henriksson, Cynthia Ní Mhurchú
| Text proposed by the Commission | Amendment |
|---|---|
| (b) re-use of data and documents already held by public authorities; | (b) re-use of data and documents already held by public authorities, in accordance with the once only principle; |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| (c) a high level of cybersecurity, and integrity of information; | (c) a high level of cybersecurity, and integrity of information, corresponding to the highest level of protection between the requirements applicable at national level and those applicable at Union level; |
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Sigrid Friis, Dan Barna, Yvan Verougstraete, Elisabetta Gualmini, Anna-Maja Henriksson, Cynthia Ní Mhurchú
| Text proposed by the Commission | Amendment |
|---|---|
| (c) a high level of cybersecurity, and integrity of information; | (c) a high level of cybersecurity, integrity of information, and the protection of sensitive and confidential information; |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| (da) protection of confidential business information, personal data and commercially sensitive information, while ensuring public access to environmental information in accordance with applicable Union law; |
| Text proposed by the Commission | Amendment |
|---|---|
| (da) all relevant publicly available geological and subsurface data necessary for the development of renewable energy for use in the installation or nearby consumption; |
| Text proposed by the Commission | Amendment |
|---|---|
| (da) secure interoperability and high standards of digital compliance; |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| (db) traceability of the main procedural steps, including the date of submission, requests for additional information, consultations carried out, opinions received and final decisions adopted; |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Brando Benifei, Stefano Bonaccini, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| (dc) accessibility for small and medium-sized enterprises, including through user-friendly interfaces and guidance in plain language; |
| Text proposed by the Commission | Amendment |
|---|---|
| (ca) all relevant publicly available geological and subsurface data necessary for the developments of renewable energy for use in the installation or nearby consumption; |
Share of geological and subsurface data, in a coordinated way, can substantially de-risk investment into renewable energy or multi-functional technologies that provide access to critical heat and raw materials simultaneously such as geothermal-energy technologies, as uncertainty remains a defining challenge for project development.
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The use of European Business Wallets or other digital tools shall not replace or limit public consultation, stakeholder involvement or any other procedural rights provided under Union or national law. Member States shall ensure that digitalisation facilitates, rather than restricts, public participation and access to relevant information. |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Member States shall ensure that project promoters, in particular small and medium-sized enterprises, have access to effective human assistance in using the single access point. They shall also ensure that an alternative channel for submission or tracking is in place in the event of prolonged technical unavailability of the single access point. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Member States may maintain separate application procedures and distinct permit decisions across relevant statutory authorities under national law. The designated contact point shall coordinate administrative workflows between competent entities without requiring a single integrated application or a single comprehensive decision. |
This amendment puts forward a operational provision that safeguards national administrative autonomy and multi-authority structures, clarifying that contact point coordination does not mandate a single application or a single comprehensive decision.
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. Member States may designate or adapt existing national single contact points and permitting platforms, provided that they meet the requirements of this Article and ensure interoperability with European Business Wallets in accordance with applicable Union law. The single access points shall use open standards and standardised interfaces, where available, and shall not make access conditional on the use of a particular commercial provider or optional service. Project promoters shall not be required to resubmit information or documents already validly transmitted or lawfully available to the relevant competent authorities, unless an update is necessary or access is restricted by law. Reuse shall remain subject to applicable data-protection requirements and shall not prevent checks necessary to establish compliance with substantive legal requirements. |
Simplification should combine interoperable national systems, open standards and the once-only principle without creating vendor lock-in. Valid electronic evidence should not trigger duplicate submissions, while necessary substantive checks remain possible.
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union, national or regional digital infrastructure, catalogues and building blocks established by Union law, including the Single Digital Gateway, while ensuring interoperability with national, regional and local permitting systems and avoiding duplication with existing single points of contact established under Union law, including Regulation (EU) 2024/1735. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. The single point of contact shall coordinate all requests for information from the competent authorities and ensure that project promoters are not required to engage separately with multiple competent authorities, except where this is strictly necessary. |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When providing the digital single access point, Member States may enable the use of the European Business Wallet in accordance with [Proposal for a Regulation on the establishment of European Business Wallets], and, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall enable the use of the European Business Wallet in accordance with [Proposal for a Regulation on the establishment of European Business Wallets], and , where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall enable the use of the European Business Wallet in accordance with [Proposal for a Regulation on the establishment of European Business Wallets], and, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. |
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Giovanni Crosetto
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When providing the digital single access point, Member States shall enable the use of the European Business Wallet in accordance with [Proposal for a Regulation on the establishment of European Business Wallets] and, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. |
European digital tools should simplify procedures, not force Member States to replace systems in which they have already invested. The European Business Wallet should therefore complement existing national infrastructure and help deliver genuine interoperability and lower administrative costs.
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law, as well as artificial intelligence and other digital tools. |
Andrea Wechsler, Christian Ehler, Angelika Niebler, Jens Gieseke, Andreas Schwab, Norbert Herhammer, Hildegard Bentele, Markus Ferber, Eszter Lakos, Oliver Schenk, Christian Doleschal, Monika Hohlmeier, Verena Mertens, Ralf Seekatz, Marie-Sophie Christ, Alexandra Mehnert, Norbert Lins, Zala Černilec Tomašič, Marion Walsmann, Jörgen Warborn, Tomas Tobé, Arba Kokalari
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law as well as artificial intelligence and other digital tools. |
The use of digital tools and artificial intelligence can help Member States deliver faster, simpler and more predictable permitting procedures. This supports a modern administration and reduces burdens for authorities.
| Text proposed by the Commission | Amendment |
|---|---|
| 3. When setting up the single access points, Member States shall, where appropriate, make use of existing Union digital infrastructure, catalogues and building blocks established by Union law. | 3. When setting up the single access points, Member States shall, where appropriate, make use of existing national or Union digital infrastructure, catalogues and building blocks established by Union law. |
From local perspective, certain recently introduced administrative frameworks (e.g. in renewable energy, critical raw materials, and net-zero projects) have not simplified permitting procedures; in some cases, they have increased complexity. Proposed requirements can and should be implemented primarily through existing national administrative systems.
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Single access points shall ensure appropriate access controls, secure information exchange and protection of commercially sensitive information. Requests for data and access to data shall be limited to what is necessary for the relevant procedure and the statutory tasks of the recipient. The systems shall provide auditable access records and measures to prevent unauthorised access, disclosure or exfiltration, including unlawful access by third-country authorities or entities. European Business Wallets and associated services used for the purposes of this Article shall comply with the provider, cybersecurity and data-location requirements laid down in the applicable Union legislation governing those wallets. Classified information and information whose disclosure could prejudice national security shall be processed only through systems authorised for that purpose under applicable Union or national law. The use of a single access point shall not require the disclosure of such information to authorities or persons not authorised to receive it. |
Digital permitting must protect sensitive industrial and defence information through data minimisation, auditable access and safeguards against unauthorised third-country access. The IAA must apply, not dilute, the security and provider requirements governing European Business Wallets.
Nicolás González Casares, Javier Moreno Sánchez, Leire Pajín, Idoia Mendia, José Cepeda, Elena Sancho Murillo, Sandra Gómez López, Lina Gálvez, Juan Fernando López Aguilar, Alicia Homs Ginel, Hana Jalloul Muro, Laura Ballarín Cereza
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Member States may designate, at the appropriate regional level, a strategic project coordinator responsible for facilitating, coordinating and monitoring the permit-granting procedures and other administrative procedures applicable to industrial manufacturing projects under this Regulation. The strategic project coordinator shall support the operation of the single access point referred to in paragraph 1 and ensure effective coordination between the competent authorities at national, regional and local level. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Bruno Tobback, Elisabeth Grossmann, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Member States shall designate, at the appropriate regional level, a strategic project coordinator responsible for facilitating, coordinating and monitoring the permit-granting procedures and other administrative procedures applicable to industrial manufacturing projects under this Regulation. The strategic project coordinator shall support the operation of the single access point referred to in paragraph 1 and ensure effective coordination between the competent authorities at national, regional and local level. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. To ensure effective implementation of the regulation and reduce delays in permitting, Member States shall ensure that the single access point authority is provided with the financial, human and technological resources necessary to carry out its tasks effectively. To that end, Member States shall establish predictable, multiannual funding frameworks dedicated, inter alia, to assisting public authorities in digitalising their procedures and providing training to personnel. |
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Barry Andrews, Dan Barna, Yvan Verougstraete, Elisabetta Gualmini, Anna-Maja Henriksson, Cynthia Ní Mhurchú
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. The Commission shall issue harmonized guidance and digital standards for the establishment and operation of the single digital access point. | |
| Upon request by a Member State, the Commission shall assist the authorities of that Member State in establishing and operating a single digital access point, in support of implementation of this Regulation. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. The single access point shall provide the project promoter with a single checklist identifying all permits, authorisations, assessments and information required for the project, as well as a consolidated timetable covering the different stages of the permit-granting procedure. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Throughout the permit-granting procedure the once-only principle shall apply. Applicants shall not be required to resubmit data or documents already lawfully held by a public authority or available through Union customs, product, permitting or business-wallet systems. |
Andrea Wechsler, Christian Ehler, Angelika Niebler, Jens Gieseke, Andreas Schwab, Norbert Herhammer, Hildegard Bentele, Markus Ferber, Oliver Schenk, Christian Doleschal, Monika Hohlmeier, Verena Mertens, Ralf Seekatz, Marie-Sophie Christ, Alexandra Mehnert, Norbert Lins, Zala Černilec Tomašič, Marion Walsmann, Jörgen Warborn, Tomas Tobé, Arba Kokalari
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Throughout the permit-granting procedure the once-only principle shall apply. Applicants shall not be required to resubmit data or documents already lawfully held by a public authority or available through Union customs, product, permitting or business-wallet systems. |
The amendments strengthen the digital and administrative simplification function of the single access points. They promote the use of artificial intelligence and other digital tools to accelerate and streamline permitting procedures and introduce a clear once-only principle so that applicants are not required to repeatedly submit information already available to public authorities. This reduces duplication, administrative burden and delays while making better use of existing Union digital infrastructure.
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Member States shall ensure that the single access points and the competent authorities have a sufficient number of qualified staff and sufficient financial, technical and technological resources to carry out their tasks under this Regulation effectively. |
Unlike Regulations (EU) 2024/1735 and (EU) 2024/1252, the proposal contains no obligation to equip the competent authorities with adequate resources. Without administrative capacity, shorter time limits on paper will not lead to faster procedures in practice.
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Member States may also allow the submission of applications through existing national digital platforms that provide equivalent functionality and interoperability, without making use of European Business Wallets mandatory. |
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Barry Andrews, Dan Barna, Brigitte van den Berg, Anna-Maja Henriksson, Cynthia Ní Mhurchú
| Text proposed by the Commission | Amendment |
|---|---|
| 3b. Member States shall ensure that SME support mechanisms are integrated within the single digital access point. These shall include a dedicated and free-of-charge SME helpdesk providing easily accessible and tailored guidance and administrative assistance to SMEs throughout the permit-granting procedure, including early advice on navigating the requirements and procedures under this Regulation, standardized templates and checklists, and access to relevant information. |
| Text proposed by the Commission | Amendment |
|---|---|
| Article 4a | |
| Safeguarding national, regional and local competences | |
| The single access point shall act as a coordinating and facilitating interface between project promoters and the competent authorities. It shall not replace the authorities competent under national law. | |
| The establishment and operation of the single access point shall build, to the extent possible, on existing national, regional and local administrative structures and shall respect the allocation of competences under national law. | |
| The establishment of the single access point shall not entail the transfer, limitation or duplication of planning, permitting or decision-making powers conferred under national law on regional or local authorities without the agreement of those authorities. | |
| Existing national, regional and local digital permitting systems shall, where appropriate, be integrated into, or made interoperable with, the single access point. |
Single access points should facilitate and coordinate procedures without creating parallel administrative structures or altering the allocation of competences under national law. This is necessary to preserve the responsibilities of local and regional authorities, in particular as regards spatial planning, permitting, infrastructure and public services.
| Text proposed by the Commission | Amendment |
|---|---|
| Article 4a | |
| Digital Coordination and Administrative Flexibility | |
| 1. Member States may establish new or maintain existing national digital coordination mechanisms and single digital portals for the management of permit-granting processes. | |
| 2. The application of standard Union digital procedures or centralised platforms under this Regulation shall not preclude Member States from utilising existing national digital infrastructure and administrative workflows, provided that such mechanisms satisfy the operational objectives and time limits for streamlining permit-granting procedures established under this Regulation. |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| Permit-granting procedure | Single application for permitting |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Jorge Martín Frías, Hermann Tertsch, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall designate, at national or regional level and in accordance with their internal institutional and constitutional framework, at least one authority responsible for coordinating with the competent authorities, with a view to establishing and maintaining a single permitting procedure enabling the applicant to submit a single application containing all the information required to obtain the permits relevant to a specific industrial manufacturing project. The designation of the coordinating authority shall not confer decision-making power in the permit-granting procedure. Member States may designate, as coordinating authority, an existing single point of contact for productive activities or for special economic zones. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. Where permits relate to specific installations, sites and emissions, such application should be established without merging their legal bases or affecting the substantive requirements, assessment procedures or permit-specific conditions applicable under Union or national law. |
This amendment clarifies that permits that are installation specific, especially "permits for operations" should not be merged with other permitting procedures, for instance at construction stage, for upgrades or change of projects.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. Project promoters are entitled but not obliged to make use of the single application. By way of derogation, applications for contractual grid connection arrangements are excluded from a single permit-granting procedure. |
In large industrial projects it may not be reasonable or even possible to apply for all the necessary permits at the beginning, as the need of permits may evolve during the project. Thus, it should be clarified that the applicants can choose between using a single application or relying on separate applications for the permits. Furthermore, Grid connection applications should be excluded from the single permit-granting procedure as they are fundamentally different from administrative permits. While building, environmental and other authorisations are granted through unilateral administrative decisions by competent authorities, grid connections are initiated through a connection application submitted by the project developer and result in a technical and financial connection proposal issued by the system operator. If accepted, this proposal leads to the conclusion of a bilateral connection contract between the system operator and the network user.
Andrea Wechsler, Christian Ehler, Angelika Niebler, Jens Gieseke, Andreas Schwab, Norbert Herhammer, Hildegard Bentele, Markus Ferber, Eszter Lakos, Oliver Schenk, Christian Doleschal, Monika Hohlmeier, Verena Mertens, Ralf Seekatz, Marie-Sophie Christ, Alexandra Mehnert, Norbert Lins, Marion Walsmann, Jörgen Warborn, Tomas Tobé, Arba Kokalari
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects in accordance with existing permit-granting regimes such as, inter alia, defined in the Directive to accelerate permit-granting procedures for energy infrastructure 2025/0400 (COD). |
The amendment clarifies that grid connection procedures remain governed by the relevant energy infrastructure and grids legislation, avoiding overlapping or conflicting permitting regimes and ensuring legal certainty.
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Giovanni Crosetto
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects including sustainable carbon processes, such as recycling ones. The use of that single permit-granting procedure shall be at the discretion of the project promoter. |
To effectively improve the functioning of the internal market by establishing a framework to support the development, competitiveness and resilience of the Union's manufacturing sector, it is necessary to explicit assure that also sustainable carbon process - such as recycling technologies - related to strategic sectors listed in Annex I could benefit of the same or similar permit-granting procedure via IAA or the Circular Economy Act. Simplification should give businesses a faster route to investment, not force them into a new procedure where existing ones already work effectively. Project promoters should therefore be free to use the single procedure when it provides real added value.
Kamila Gasiuk-Pihowicz, Krzysztof Hetman, Borys Budka, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas, Mirosława Nykiel
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish or designate a coordinated permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects, without prejudice to sector-specific procedures and competences under Union or national law. |
Krzysztof Hetman, Kamila Gasiuk-Pihowicz, Borys Budka, Mirosława Nykiel, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. The use of that single permit-granting procedure shall be at the discretion of the project promoter. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. Project promoters are entitled but not obliged to make use of the single application. |
In large industrial projects it may not be reasonable or even possible to apply for all the necessary permits at the beginning, as the need of permits may evolve during the project. Thus, it should be clarified that the applicants can choose between using a single application or relying on separate applications for the permits.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects including sustainable carbon processes, such as recycling. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects, in accordance with existing permit-granting regimes. |
Klara Dostalova, Jaroslava Pokorná Jermanová, Tomáš Kubín, Jaroslav Bžoch, Ondřej Knotek, Jana Nagyová, Jaroslav Knot, Anna Bryłka, Virginie Joron, Isabella Tovaglieri, Paolo Borchia
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall ensure a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. |
Single permit procedures in manufacturing projects in many cases require coordination of both private-law and public-law authorisations. Given the constitutional protection of private-law relations and their frequent role as a prerequisite for public-law permits, such an approach could introduce significant procedural complexity and increase project costs.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Member States shall establish a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. | 1. Member States shall ensure a single permit-granting procedure based on a single application covering all permits required for industrial manufacturing projects. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. Member States shall ensure that the competent authority coordinates all relevant authorities involved in the permit-granting procedure and that the comprehensive decision is adopted within a clearly defined maximum deadline. | |
| Where an authority consulted in the permit-granting procedure fails to provide its opinion within the applicable deadline, Member States shall ensure that the procedure may continue, without prejudice to applicable Union environmental law. | |
| Successive requests for additional information shall be limited to what is strictly necessary and shall not be used to unduly prolong the procedure. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States shall establish or designate one or more competent authorities as the single point of contact at the relevant administrative level to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. Member States may designate the authority or authorities already established as the single point of contact pursuant to Article 6 of Regulation (EU) 2024/1735. Member States shall ensure that the authorities concerned have adequate administrative, technical, financial and digital capacity to carry out their tasks effectively, including through technical assistance, training and the sharing of expertise, with particular attention to the capacity of regional and local authorities. |
Accelerated permitting requires adequately staffed and resourced authorities. Strengthening administrative, technical, financial and digital capacity, particularly at regional and local level, addresses structural causes of delay without lowering procedural or environmental standards.
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Jessika van Leeuwen, Giovanni Crosetto
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States shall designate, at national or regional level in accordance with their internal institutional and constitutional framework, at least one coordinating authority to facilitate timely decision-making by the relevant competent authorities in the context of the permit-granting procedure referred to in paragraph 1 in accordance with Union and national law. The designation of the coordinating authority shall not confer decision-making power in the permit-granting procedure. Member States may designate as coordinating authority an existing single point of contact for productive activities or for special economic zones. |
Faster permitting requires coordination, not a transfer of competences. Member States should be free to build on the authorities and single desks that already operate effectively at national or regional level, while preserving their institutional structures and avoiding the creation of parallel administrations.
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within 12 months of the application being acknowledged as complete pursuant to paragraph 3. Where the competent authority has not issued the comprehensive decision within that period, the permits covered by the application shall be deemed granted, unless the competent authority has, before the expiry of that period, issued a duly reasoned decision extending the deadline by a specified and reasonable period. |
Krzysztof Hetman, Kamila Gasiuk-Pihowicz, Borys Budka, Mirosława Nykiel, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. The coordinating authority shall coordinate the authorities involved, monitor compliance with applicable deadlines, identify bottlenecks and facilitate escalation where the applicable time limits are at risk of being exceeded, without prejudice to the decision-making competences of the authorities concerned. |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States shall establish or designate one or more competent authorities to act as a one-stop-shop, at the administrative level they deem appropriate, to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issuing of a comprehensive decision within the applicable time limit. To this end, Member States may designate the authority or authorities already established as a one-stop-shop pursuant to Article 6 of Regulation (EU) 2024/1735. |
Raúl de la Hoz Quintano, Adrián Vázquez Lázara, Esteban González Pons, Pilar del Castillo Vera, Dolors Montserrat, Javier Zarzalejos, Susana Solís Pérez, Borja Giménez Larraz, Carmen Crespo Díaz, Antonio López-Istúriz White, Esther Herranz García, Nicolás Pascual de la Parte, Juan Ignacio Zoido Álvarez, Francisco José Millán Mon, Maravillas Abadía Jover, Isabel Benjumea Benjumea, Gabriel Mato
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States, without prejudice to the allocation of competences, shall designate a competent authority at the relevant administrative level to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. Member States may designate an existing competent authority established under Union or national law for this purpose. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit falling within the scope of this Regulation. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Member States shall designate a single point of contact to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 2. Member States shall designate a competent authority to coordinate the permit-granting procedure referred to in paragraph 1 in order to ensure the adoption and issue of a comprehensive decision within the applicable time limit. | 2. Project promoters shall access the permitting application procedure via the digital single access point referred to in Article 4. The use of the single submission shall be at the discretion of the project promoter. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The single point of contact referred to in paragraph 2 shall be responsible for the functional procedural subordination, the overall procedural management, facilitation and coordination of the environmental assessment procedure under this Regulation. | |
| For those purposes it shall: | |
| (i) organise and set out the order of the procedural steps of the environmental assessment in accordance with Article 7; | |
| (ii) coordinate the submission and exchange of all necessary documents and information for environmental assessments; | |
| (iii) facilitate interactions between the competent authorities It shall provide information on when an application is considered to be completed in accordance with Article 7 of this Regulation and notify the project developer of the outcome of the reasoned conclusion. | |
| The responsibilities of the environmental single point of contact laid down in this paragraph shall be without prejudice to the responsibilities of competent authorities in line with Article 1, paragraph 2, point (g), points (ii), (iii), (iv) and (v) of Directive 2011/92/EU. |
João Cotrim De Figueiredo, Morten Løkkegaard, Dan Barna, Engin Eroglu, Benoit Cassart, Bart Groothuis, Jeannette Baljeu
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Where a project promoter makes use of the single permit-granting procedure referred to in paragraph 1, the coordinating authority shall act as the single point of contact for the project promoter throughout the procedure. Member States may designate an authority already established pursuant to Article 6 of Regulation (EU) 2024/1735 for that purpose. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. When designating the competent authority, Member States shall use existing competent authorities and single points of contact wherever those bodies can perform the tasks laid down in this Regulation; |
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. Where an industrial manufacturing acceleration area overlaps totally or in part with a Net-Zero Acceleration Valley, the single point of contact designated pursuant to Article 18(1) of Regulation (EU) 2024/1735 shall also coordinate the permit-granting procedures this regulation for projects within the overlapping area. Member States should ensure that that single point of contact has the necessary competences and resources and shall avoid any parallel coordination structures. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. Where a single point of contact exists or is required for an overall permit-granting process pursuant to other Union or national legislation, the environmental single point of contact referred to in paragraph 1 shall be the same as the one established for that overall permit-granting procedure. |
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 30 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. The request shall identify all missing information and the legal basis for requiring it. Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 15 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. If the competent authority neither acknowledges completeness nor requests missing information within the applicable deadline, the application shall be deemed complete for the sole purpose of starting the time limit for the permit-granting procedure. This shall not constitute authorisation to carry out the project. |
The completeness stage must not become an indefinite administrative holding period. Shorter deadlines and a limited deemed-completeness rule start the clock without granting permits by silence.
Kamila Gasiuk-Pihowicz, Krzysztof Hetman, Borys Budka, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas, Mirosława Nykiel
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, or no later than 90 days for projects requiring an environmental impact assessment, an industrial emissions permit, a major-accident prevention assessment, a grid connection assessment or a critical infrastructure or cybersecurity assessment the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. |
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. If, on expiry of this period, the competent authority has not confirmed receipt of the application or requested further information, the application shall be deemed to be complete and the authorisation procedure shall commence. |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 45 days from the receipt of an application for a permit for industrial manufacturing projects, the relevant competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application, via the digital single access point. |
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 30 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. |
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 30 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. |
If the aim of the regulations is to simplify the procedures for issuing permits for the construction, reconstruction, or expansion of industrial facilities, then these procedures should be shorter. Public administration bodies typically issue building permits within 65 days; therefore, an optimal solution to accelerate the permitting process would be to introduce a 30-day deadline for verifying the completeness of the application.
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 30 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. |
Scopul regulamentului este accelerarea capacității industriale. Pentru ca procedura unică de autorizare să producă efecte reale, verificarea caracterului complet al cererii trebuie să se realizeze într-un termen cât mai scurt și previzibil. Reducerea termenului de la 45 la 30 de zile și a termenului pentru o eventuală a doua solicitare de la 30 la 15 zile contribuie la reducerea întârzierilor administrative și la crearea unui cadru mai predictibil pentru investițiile industriale. Unul dintre riscurile procedurilor administrative este prelungirea succesivă a procesului prin solicitări suplimentare de documente. Pentru ca procedura unică de autorizare să fie efectivă, investitorul trebuie să beneficieze de un nivel suficient de certitudine cu privire la caracterul complet al dosarului. Excepția propusă păstrează posibilitatea autorității de a solicita informații care, în mod obiectiv, nu puteau fi identificate anterior.
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 30 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. |
| Text proposed by the Commission | Amendment |
|---|---|
| No later than 45 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. | No later than 30 days from the receipt of the application for a permit for industrial manufacturing projects, the competent authority shall either acknowledge that the application is complete or request any missing information needed to process the application. |
Kamila Gasiuk-Pihowicz, Krzysztof Hetman, Borys Budka, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas, Mirosława Nykiel
| Text proposed by the Commission | Amendment |
|---|---|
| Provisions in subparagraph 1 shall not prevent the competent authority, other competent authorities or network operators involved in the procedure from requesting additional information where such information is necessary for environmental assessment, industrial emissions permitting, chemical safety, prevention of major accidents, water protection, critical infrastructure protection, cybersecurity, or for assessing the technical feasibility, secure operation and capacity availability of electricity, gas, hydrogen, carbon dioxide or heat networks. Any such request shall be reasoned, proportionate and limited to the information necessary for the relevant assessment. |
Kamila Gasiuk-Pihowicz, Krzysztof Hetman, Borys Budka, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas, Mirosława Nykiel
| Text proposed by the Commission | Amendment |
|---|---|
| The provisions of this Article shall not affect the right and obligation of transmission system operators, distribution system operators or other regulated network operators to assess, refuse, condition or sequence connection requests on the basis of technical feasibility, system security, capacity availability, network development plans or other applicable sector-specific requirements. |
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 15 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. Once the time limit laid down in this paragraph has elapsed , no new request for completeness may be made, unless the relevant information cannot reasonably be identified based on the application and the documents available at the time. |
Scopul regulamentului este accelerarea capacității industriale. Pentru ca procedura unică de autorizare să producă efecte reale, verificarea caracterului complet al cererii trebuie să se realizeze într-un termen cât mai scurt și previzibil. Reducerea termenului de la 45 la 30 de zile și a termenului pentru o eventuală a doua solicitare de la 30 la 15 zile contribuie la reducerea întârzierilor administrative și la crearea unui cadru mai predictibil pentru investițiile industriale. Unul dintre riscurile procedurilor administrative este prelungirea succesivă a procesului prin solicitări suplimentare de documente. Pentru ca procedura unică de autorizare să fie efectivă, investitorul trebuie să beneficieze de un nivel suficient de certitudine cu privire la caracterul complet al dosarului. Excepția propusă păstrează posibilitatea autorității de a solicita informații care, în mod obiectiv, nu puteau fi identificate anterior.
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed by the relevant competent authority to be incomplete, the competent authority may within 30 days of the submission of the requested missing information, make a second request for any outstanding information via the digital single access point. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. In duly justified circumstances, the relevant competent authority can request additional information not previously requested where not doing so would result in the rejection of the application. |
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Giovanni Crosetto
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. In duly justified circumstances, the relevant competent authority may request additional information not previously requested where not doing so would result in the rejection of the application. |
Predictable deadlines are essential for industrial investment, but simplification should not result in viable projects being rejected because an authority is prevented from requesting information that proves indispensable at a later stage. The procedure should combine certainty for investors with sufficient flexibility to reach a sound decision.
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the single point of contact may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The single point of contact shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. |
| Where other Union legislation establishes shorter timelines than the ones set out in paragraph 3 of this Article, those shorter deadlines shall apply. |
The AM seeks to ensure that deadlines established under this Regulation do not undermine shorter deadlines provided for other Union legislations. It preserves the more stringent requirements in order to prevent unece3ssary administrative delays.
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may make a second request for any information still missing, provided that the total time limit for checking the completeness of the application does not exceed 45 days from its receipt. |
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, only where necessary and without suspending the processing of the application, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. |
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 14 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. |
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 15 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. |
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 15 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. |
João Cotrim De Figueiredo, Morten Løkkegaard, Dan Barna, Engin Eroglu, Benoit Cassart, Bart Groothuis, Jeannette Baljeu
| Text proposed by the Commission | Amendment |
|---|---|
| Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request for any information still missing. The competent authority shall not request information in areas not covered in the first request for additional information and shall request further information only as necessary to cover the missing information. | Where, after the submission of any missing information, the application is still deemed to be incomplete, the competent authority may, within 30 days of the submission of the requested missing information, make a second request limited to the information necessary to complete the elements specifically identified in the first request. No new category of information may be requested unless this is justified by material new circumstances arising after the first request. |
No moving goalposts. Once the administration tells the applicant what is missing, it should not repeatedly open new information requirements.
| Text proposed by the Commission | Amendment |
|---|---|
| Any time limit applicable to the permit-granting procedure shall start to run only from the date on which the complete application has been submitted. | |
| The running of that time limit may be suspended where: | |
| (a) information or documentation required pursuant to Union or national law remains outstanding; | |
| (b) the project promoter makes substantial modifications to the project; or | |
| (c) environmental assessments, public participation procedures or other procedural steps required pursuant to Union or national law cannot reasonably be completed within that time limit for reasons not attributable to the competent authority. | |
| Any suspension pursuant to this subparagraph shall be duly justified and shall not exceed the time necessary to complete the relevant procedural step. |
Accelerated procedures should remain compatible with legal certainty and with applicable requirements concerning environmental assessments and public participation. Procedural time limits should therefore start to run only once a complete application has been submitted.
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| If, within the 45-day period referred to in the first subparagraph, there has been no confirmation that the application is complete, or no request for missing information has been made, authorisation shall be deemed to have been granted, except where the industrial manufacturing project is likely to affect public health or national security, in which case the competent authority remains obliged to take an express decision on the application. |
João Cotrim De Figueiredo, Morten Løkkegaard, Dan Barna, Engin Eroglu, Bart Groothuis, Jeannette Baljeu
| Text proposed by the Commission | Amendment |
|---|---|
| Member States shall establish and publish a clear and proportionate maximum time limit for the permit-granting procedure referred to in this Article, starting from the date on which the application is considered complete pursuant to paragraph 3. The maximum time limit shall take into account the nature and complexity of the project. |
A simpler procedure is of limited value if companies do not know when it will end. Once an application is complete, the project promoter should have a published, predictable and proportionate maximum timeline covering the whole administrative procedure.
| Text proposed by the Commission | Amendment |
|---|---|
| The competent authority shall adopt and notify the final decision within a binding maximum period of 90 days from the date on which the application is confirmed to be complete. If the authority fails to issue a decision within this timeframe, the principle of tacit approval shall apply. |
| Text proposed by the Commission | Amendment |
|---|---|
| Where the competent authority has not adopted and notified the comprehensive decision referred to in paragraph 2 within the applicable time limit, the permits covered by the application shall be deemed to have been granted upon expiry of that time limit. |
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Yvan Verougstraete, Anna-Maja Henriksson, Cynthia Ní Mhurchú
| Text proposed by the Commission | Amendment |
|---|---|
| The time limits set in this Article shall be without prejudice to any shorter time limits set by Member States. |
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Dan Barna, Yvan Verougstraete, Elisabetta Gualmini, Anna-Maja Henriksson, Cynthia Ní Mhurchú
| Text proposed by the Commission | Amendment |
|---|---|
| The acknowledgment of the completeness of the application, any request for missing information or documents, and any decision concerning the application shall be communicated to the applicant through the single digital access point. |
| Text proposed by the Commission | Amendment |
|---|---|
| Member States shall ensure that the project promoter may obtain, without undue delay, a certificate confirming the tacit approval, which shall have the same legal effects as the corresponding express decision. |
| Text proposed by the Commission | Amendment |
|---|---|
| The subparagraph 2 a (new) shall not apply where Union law requires an express decision by the competent authority or where tacit approval would be incompatible with obligations arising from Union law. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. The permit-granting procedure shall not exceed 12 months from the acknowledgement, or deemed acknowledgement, that the application is complete. For the conversion or extension of an existing industrial site, that period shall not exceed six months. The competent authority may extend the applicable period once, by no more than three months, where exceptional circumstances relating to the nature, complexity, location or size of the project make this necessary. It shall notify the project promoter of the reasons for the extension and the revised timetable before the original deadline expires. Those periods shall include environmental assessments required under Union law. Where a longer period is indispensable to comply with a specific procedural requirement of Union law, the competent authority shall identify that requirement, substantiate the additional time needed and notify a revised timetable to the project promoter. Shorter time limits under other Union legislative acts shall remain applicable. Expiry of a time limit shall not constitute authorisation to carry out the project. |
A single procedure needs an enforceable timetable to provide investment certainty. The amendment accelerates upgrades to existing sites while preserving environmental obligations and more favourable sector-specific rules.
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Member States shall ensure that the authorisation procedure referred to in this Article is completed within a specific and proportionate maximum time limit, starting from the date of submission of the complete application referred to in paragraph 3. This time limit covers all stages of the procedure, including environmental assessments, the collection of opinions and the obtaining of required permits, as well as the adoption of the final decision. Member States shall ensure that the time limit is set in such a way as to strike a fair balance between, on the one hand, the objective of simplifying and speeding up procedures, and, on the other hand, compliance with the other provisions of the applicable law. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Member States shall ensure that the permitting procedure referred to in this Article is concluded within a certain and proportionate maximum time limit, starting from the date of submission of the complete application referred to in paragraph 3. Such time limit shall cover all stages of the procedure, including environmental assessments, the acquisition of opinions and clearances, as well as the adoption of the final decision. Member States shall ensure that the time limit is defined so as to guarantee an appropriate balance between the need for simplification and acceleration of procedures and compliance with environmental standards and other applicable legislation. |
Member States should define a proportionate time limit, taking account of national circumstances and applicable environmental and other legal requirements in order to make the maximum duration of the permitting procedure predictable.
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. No later than two months from the date of the receipt of the application, the single point of contact shall draw up, in close cooperation with other authorities concerned, a detailed schedule for the permit-granting process. That schedule shall start from the moment when the single point of contact acknowledges the completeness of the application. The schedule shall be published by the single point of contact on the single digital access point. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. Project promoters of industrial manufacturing projects whose permit-granting procedures are pending on [OP: please insert the date of application of this Article] may request that those procedures be continued in accordance with this Article, including the applicable time limits. Information and documents already submitted shall not be requested again. |
Projects which have been waiting for a permit for several years should not be treated less favourably than new projects. Promoters of pending procedures should be able to benefit from the streamlined procedure without having to resubmit their applications.
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Dan Barna
| Text proposed by the Commission | Amendment |
|---|---|
| 3a. For strategic decarbonization and net-zero projects implemented on existing industrial sites, competent authorities shall not require new environmental impact assessment screening procedure, provided that the project does not result in an increase in emissions beyond the levels authorized under the existing permit. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3b. Member States shall provide the competent authorities with the necessary resources, legal and administrative means for performing the tasks set out in this Regulation, and shall ensure that project promoters have access to sufficient and effective human support throughout the permitting procedure, provided free of charge and within a reasonable timeframe. |
| Text proposed by the Commission | Amendment |
|---|---|
| 3b. This Article shall be without prejudice to shorter time limits laid down in national law. Member States shall report annually to the Commission on the average and maximum duration of permit-granting procedures for industrial manufacturing projects. The Commission shall publish a comparative overview of those reports every year. |
Shorter national time limits should be preserved, in line with Regulations (EU) 2024/1735 and (EU) 2024/1252. Annual reporting and a public comparative overview will ensure that the acceleration of permitting is effectively implemented in all Member States.
Nikola Minchev, Bart Groothuis, Christophe Grudler, Jeannette Baljeu, Sandro Gozi, Morten Løkkegaard, Yvan Verougstraete, Karin Karlsbro, Anna-Maja Henriksson, Cynthia Ní Mhurchú
| Text proposed by the Commission | Amendment |
|---|---|
| 3b. Member States shall ensure that the single digital access points and all competent authorities involved have sufficient qualified staff and financial, digital and technical resources for the effective performance of their tasks under this Regulation. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall apply also where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. |
| Where multiple regulatory frameworks apply concurrently, the competent authority shall apply the procedural regime and applicable deadlines that are most favourable to and least burdensome for the applicant undertaking. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. Where rules to streamline administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors, the project promoter shall be entitled to opt for the procedural regime which is more favourable to it. For that purpose, the project promoter may choose between the procedure laid down in this Article and the applicable procedure laid down in the relevant Union legislative act. |
Klara Dostalova, Jaroslava Pokorná Jermanová, Tomáš Kubín, Jaroslav Bžoch, Ondřej Knotek, Jana Nagyová, Jaroslav Knot, Anna Bryłka, Virginie Joron, Isabella Tovaglieri, Paolo Borchia, Enikő Győri, András Gyürk, Ernő Schaller-Baross, András László
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors, or where equivalent streamlined procedures exist under national law ensuring comparable outcomes and time. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors, or where equivalent streamlined procedures exist under national law ensuring comparable outcomes and time. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors, including permit-granting processes for environmental assessments. |
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Nicolas Bay, Giovanni Crosetto, Marion Maréchal
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply where specific permit-granting or licensing procedures, requirements or rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. |
The IAA should simplify Europe's regulatory framework, not add a second permitting regime on top of sector-specific rules that already apply. Where Union legislation already provides dedicated procedures, those frameworks should remain the reference point for businesses and administrations.
Krzysztof Hetman, Kamila Gasiuk-Pihowicz, Borys Budka, Mirosława Nykiel, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply only where and to the extent that rules to streamline the administrative and permit-granting processes are established in other Union legislative acts and apply to the specific industrial manufacturing project concerned. |
Jorge Martín Frías, Hermann Tertsch, Ewa Zajączkowska-Hernik, Anna Bryłka, Sebastian Kruis, Barbara Bonte
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors and they are more favourable for the applicant. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors and they are more favourable for the applicant. |
The more favourable rules to streamline the administrative and permit-granting processes should have precedence.
| Text proposed by the Commission | Amendment |
|---|---|
| 4. The provisions of this Article shall not apply where rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. | 4. The provisions of this Article shall not apply where equivalent rules to streamline the administrative and permit-granting processes are established in other Union legislative acts for specific industrial manufacturing sectors. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4a. Member States shall ensure that the competent permitting authorities are provided with the financial, human and technological resources necessary to carry out these tasks effectively. To that end, Member States shall establish predictable, multiannual funding frameworks dedicated, inter alia, to assisting public authorities in digitalising their procedures and providing training to personnel. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4a. Where different parts of an industrial manufacturing project fall under this Regulation and other Union legislative acts, Member States shall ensure coordination between the competent authorities and reuse of information and documents already submitted, so as to avoid duplicate applications and assessments. Such coordination shall not extend the time limits applicable under those acts. |
| Text proposed by the Commission | Amendment |
|---|---|
| 4a. The permit-granting procedure referred to in paragraph 1 shall be without prejudice to the application and legal requirements of any environmental assessment or other obligation required under Union law, including those laid down in Directives 92/43/EEC, 2000/60/EC, 2004/35/EC, 2010/75/EU, 2011/92/EU and 2012/18/EU. |
Krzysztof Hetman, Kamila Gasiuk-Pihowicz, Borys Budka, Mirosława Nykiel, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas
| Text proposed by the Commission | Amendment |
|---|---|
| 4a. For the purposes of permit granting procedures under this Article, the modernisation, retrofit or conversion of existing industrial installations shall be treated on an equal footing with new industrial manufacturing projects. |
| Text proposed by the Commission | Amendment |
|---|---|
| Energy-intensive industry decarbonisation projects | Energy-intensive industry decarbonisation projects and circularity projects |
| Text proposed by the Commission | Amendment |
|---|---|
| Energy-intensive industry decarbonisation projects | Accelerating industrial manufacturing and decarbonisation permitting |
| Text proposed by the Commission | Amendment |
|---|---|
| Energy-intensive industry decarbonisation projects | Accelerating permitting for industrial manufacturing |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Ewa Zajączkowska-Hernik, Jorge Martín Frías, Hermann Tertsch, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| Energy-intensive industry decarbonisation projects | Energy-intensive industry strategic projects |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects that contribute to the maintenance, modernisation or development of industrial capacity actually located within the territory of the Union. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects and to the infrastructure for the transport, distribution and storage of energy, feedstocks and products associated with those projects. |
Access to energy, feedstocks and product logistics is vital for decarbonisation projects. The associated infrastructure should therefore benefit from the same accelerated permit-granting procedures.
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Giovanni Crosetto, Nicolas Bay, Marion Maréchal
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Member States shall apply the streamlined administrative and permit-granting processes set out in Chapter II, Section II, of Regulation (EU) 2024/1735 to energy-intensive industry decarbonisation projects as defined in Article 3, point (3), of this Regulation. |
The IAA should simplify Europe's regulatory framework, not add a second permitting regime on top of sector-specific rules that already apply. Where Union legislation already provides dedicated procedures, those frameworks should remain the reference point for businesses and administrations.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects, including projects for the production of sustainable aviation fuels as defined in Article 3, point (7), of Regulation (EU) 2023/2405 . |
Sustainable aviation fuels are essential for reducing emissions from aviation, particularly where direct electrification is not yet feasible. Scaling up European SAF production requires significant investment in new and converted industrial facilities and predictable and efficient permitting procedures. Explicitly including SAF production projects ensures that they can benefit from the accelerated permitting framework and strategic-project status provided for under this Regulation. This will support the deployment of SAF production capacity in Europe, strengthen domestic supply chains and contribute to meeting the growing demand created by the Union’s aviation decarbonisation framework.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects, and the infrastructure associated with such projects. |
Access to energy, feedstocks and product logistics (transport, distribution and storage) is vital for decarbonisation projects. Therefore, also relevant associated infrastructure should be clearly included.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects, and the infrastructure associated with such projects. |
Access to energy, feedstocks and product logistics is vital for decarbonisation projects. Therefore, also relevant associated infrastructure should be included.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all industrial manufacturing projects, and the associated infrastructure of such projects. |
The acceleration of permitting is essential for all manufacturing industries, far beyond energy-intensive industry decarbonisation projects. The associated infrastructure (transport, energy, storage, etc.) should also be covered.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects and to all circularity projects . |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply mutatis mutandis to all energy-intensive industry decarbonisation projects. |
Klara Dostalova, Jaroslava Pokorná Jermanová, Tomáš Kubín, Jaroslav Bžoch, Ondřej Knotek, Jana Nagyová, Jaroslav Knot, Anna Bryłka
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply mutatis mutandis to all energy-intensive industry decarbonisation projects. |
“Mutatis mutandis” ensures adaptation rather than mechanical application of NZIA provisions. Proposed wording: Energy-intensive industries differ structurally from net-zero technologies. Ensures proportional application.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all joint energy-intensive industry and clean technology projects. |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Ewa Zajączkowska-Hernik, Jorge Martín Frías, Hermann Tertsch, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry strategic projects. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all energy-intensive industry decarbonisation projects. | 1. Chapter II, Section II, of Regulation (EU) 2024/1735 shall apply to all industrial manufacturing projects. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. Notwithstanding Article 6, new-build nuclear power plants, including small modular reactors, the lifetime extension of existing nuclear power plants, and the industrial manufacturing projects supplying them, shall be considered strategic projects for the purposes of [Article 14 of the Proposal for a Regulation on speeding-up environmental assessment] and shall be given priority in permit-granting procedures. | |
| Nuclear energy shall be treated on an equal footing with all other low-carbon energy sources for all purposes of this Regulation. | |
| Member States shall ensure that the analysis of energy needs under Article 26, point (c), takes nuclear energy, into account. |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. In implementing this Article, Member States shall pay particular attention and give priority treatment to projects involving the modernisation, conversion or decarbonisation of existing industrial sites facing a significant risk of closure, relocation or a substantial reduction in production capacity, particularly where such projects contribute to preserving industrial employment, reducing imported emissions, preventing carbon leakage or preserving strategic value chains within the Union. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | deleted |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Estelle Ceulemans, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez, Delara Burkhardt
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment], provided that those projects contribute to the Union targets as defined notably in Regulation EU (2021/1119). Points 1, 2 and 3 of the Annex in that Regulation shall apply. |
| Where projects benefit from accelerated procedures under this Article, Member States shall ensure early and meaningful involvement of workers, trade unions, local communities and relevant stakeholders, including through access to clear and accessible information on the expected environmental, social and employment impacts of the project. | |
| Member States shall give priority, within the framework of this Article, to projects that contribute to the direct electrification of industrial processes, direct use of renewable energy, energy efficiency, waste-heat recovery, circular use of materials, reduction of critical raw material dependency, the use of RFNBOs and low-carbon hydrogen to electrify industrial processes in cases where direct electrification is technically limited or economically less viable, and the creation or retention of quality jobs in the Union. |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. All European energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to the resilience, preservation or strengthening of the Union’s strategic industrial capacity, and the security of its supply of essential industrial products, as well as decarbonisation, the avoidance of imported CO2 emissions, or the promotion of resource efficiency for the purposes of [Article 14 of the proposal for a regulation on speeding up environmental assessment]. Points 1, 2 and 3 of the Annex to that Regulation shall apply. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. Lifetime extension of existing nuclear units contributing to maintaining zero-emission electricity generation shall also be considered strategic projects in the sense of this paragraph. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. Supporting a just transition towards the Union’s 2030, 2040 and 2050 targets for energy and climate, in particular by prioritising support for promoting all energy-intensive industry decarbonisation projects which shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. |
Christophe Clergeau, Delara Burkhardt, Thomas Pellerin-Carlin, Bruno Tobback, Pierre Jouvet, Jean-Marc Germain
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. All energy-intensive industry decarbonisation and circularity projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment], provided that those projects contribute to the Union targets as defined notably in Regulation EU (2021/1119. Points 1, 2 and 3 of the Annex in that Regulation shall apply. |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Ewa Zajączkowska-Hernik, Jorge Martín Frías, Hermann Tertsch, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. Energy-intensive industry projects shall be considered strategic where they contribute to strengthening the Union’s resilience, restoring the competitiveness of its industrial base, reducing strategic dependencies, while fully respecting the principle of technological neutrality and avoiding discrimination between technologies capable of delivering industrial competitiveness, security of supply and affordability. |
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Giovanni Crosetto, Nicolas Bay, Marion Maréchal
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. Energy-intensive industry decarbonisation projects as defined in Article 3, point (3), of this Regulation shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. |
Projects that decarbonise Europe's energy-intensive industrial base are strategic for both competitiveness and climate objectives. They should therefore benefit from the accelerated environmental assessment tools available to projects that contribute to resilience, decarbonisation and resource efficiency.
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. All industrial manufacturing projects, as defined in Article 3, point (1) shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. All energy-intensive industry decarbonisation projects shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. | 2. All ‘joint energy-intensive industry and clean technology projects’ shall be considered strategic projects contributing to resilience and decarbonisation or resource efficiency for the purposes of [Article 14 of Proposal for a Regulation on speeding-up environmental assessment]. Points 1, 2 and 3 of the Annex in that Regulation shall apply. |
Raúl de la Hoz Quintano, Dirk Gotink, Tomislav Sokol, Adrián Vázquez Lázara, Esteban González Pons, Pilar del Castillo Vera, Dolors Montserrat, Javier Zarzalejos, Susana Solís Pérez, Borja Giménez Larraz, Carmen Crespo Díaz, Antonio López-Istúriz White, Esther Herranz García, Nicolás Pascual de la Parte, Juan Ignacio Zoido Álvarez, Francisco José Millán Mon, Maravillas Abadía Jover, Isabel Benjumea Benjumea, Gabriel Mato
| Text proposed by the Commission | Amendment |
|---|---|
| Temporary emissions, depositions or temporary deterioration arising directly from the construction, installation or commissioning of an energy-intensive industry decarbonisation project shall not, in themselves, preclude its authorisation, provided that such impacts are unavoidable, temporary and proportionate, appropriate mitigation measures are applied, no technically and economically feasible alternative would significantly reduce those impacts, and the project is expected to deliver a substantial net environmental improvement within a defined period. This paragraph shall not apply to permanent pollution, significant risks to human health or irreversible damage to protected ecosystems. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall adopt delegated acts in accordance with Article 30 to supplement this Regulation by laying down criteria to support Member States in determining whether a project qualifies as a joint energy-intensive industry and clean technology project where it combines the modernisation or decarbonisation of an energy-intensive industrial installation with the deployment, scale-up or related supply chains of the clean technology solutions necessary for that modernisation or decarbonisation. Those criteria shall be based on project developers’self-declaration and take into account projects implemented in successive modernisation or decarbonisation phases, provided that they deliver measurable progress towards industrial decarbonisation. |
Consistent treatment across Member States ‘joint energy-intensive industry and clean technology projects’
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Changes to, or extensions of, industrial manufacturing projects that lead to a verifiable and permanent net reduction in nitrogen emissions compared with the existing installation, including where such changes are undertaken to support the decarbonisation, energy-efficiency, or clean-technology transition of the installation, shall not be subject to a separate assessment of nitrogen emissions under Article 6(3) of Council Directive 92/43/EEC, provided that the change or extension does not, in itself, cause a significant increase in emissions of other polluting substances likely to adversely affect the conservation objectives of the Natura 2000 site concerned. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. For the purposes of this Article, energy-intensive industry decarbonization projects shall include projects concerning new installations as well as the modernization, conversion, electrification, energy efficiency improvement, heat recovery, fuel switching, use of decarbonized energy, circularity improvement or indirect-emission reduction of existing industrial installations. Member States shall ensure that such projects benefit from administrative priority, enhanced coordination between competent authorities and, where relevant, coordination with grid connection and energy infrastructure planning. |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Where a project referred to in this Article requires the creation or adaptation of or connection to infrastructure essential for its decarbonisation, in particular grid connections, energy supply infrastructure, hydrogen infrastructure, or infrastructure for the capture, transport and storage of carbon dioxide, Member States shall ensure that the relevant authorisation procedures are coordinated with the main procedure and are given equivalent priority and fast-track treatment in accordance with Union law. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Where, in the absence of criteria set under Article 6(2) or (3) of Directive 2008/98/EC, the authorisation of a circularity project requires verification pursuant to Article 6(4) of that Directive that waste has ceased to be waste, Member States shall ensure that such verification is available and is carried out within the permit-granting process. This paragraph is without prejudice to the conditions laid down in Article 6(1) of Directive 2008/98/EC. |
Krzysztof Hetman, Kamila Gasiuk-Pihowicz, Borys Budka, Mirosława Nykiel, Bogdan Andrzej Zdrojewski, Dariusz Joński, Andrzej Buła, Adam Jarubas
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Where greenhouse-gas emissions data are required under this Regulation for projects covered by Directive 2003/87/EC, existing verified data reported under the EU ETS and, where relevant, Regulation (EU) 2023/956 shall be used to the maximum extent possible. No duplicative monitoring, reporting or verification requirements shall be imposed where equivalent verified data are already available. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Projects for the supply of low-carbon heat, electricity or hydrogen dedicated to installations of energy-intensive industries, including small modular reactors located at or near industrial sites, shall be considered energy-intensive industry decarbonisation projects for the purposes of this Article. This paragraph shall be without prejudice to the requirements of Council Directive 2009/71/Euratom. |
Small modular reactors and other dedicated low-carbon heat sources are among the few options to decarbonise chemical and other plants needing high-temperature heat. Several such projects are being prepared. Granting them the same accelerated permitting as other decarbonisation projects supports technology neutrality and energy security, without affecting nuclear safety rules.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The changes or extensions of industrial manufacturing projects that result in a structural reduction of nitrogen emissions, compared to the existing project, shall not require an assessment of nitrogen emissions in an assessment that may be carried out to comply with Article 6 (3) of the Council Directive 92/43/EEC (Habitats Directive). |
Bart Groothuis, Nikola Minchev, Christophe Grudler, Jeannette Baljeu, Morten Løkkegaard, Sandro Gozi, Dan Barna, Anna-Maja Henriksson, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The changes or extensions of industrial manufacturing projects that result in a structural reduction of nitrogen emissions, compared to the existing project, shall not require an assessment of nitrogen emissions in an assessment that may be carried out to comply with Article 6 (3) of the Council Directive 92/43/EEC (Habitats Directive). |
A chemical or steel plant that switches to a cleaner process can cut its nitrogen emissions by 85%. Today it can still be refused a permit over the 15% that remains. The old, dirtier plant then keeps running. The Grids Package already exempts grids, storage and hydrogen on the same logic. This amendment does the same for industrial projects that cut emissions.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Member States are expected to carry out all necessary assessments, planning procedures, and evaluations applicable to the location of each industrial manufacturing acceleration area, excluding those that are installation specific. |
The paragraph that this amendment puts forward should reduce the administrative burdens on individual project developers by shifting territorial and location-level evaluations to national authorities prior to project-specific applications.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Member States shall not be required to introduce or extend systems of tacit approval where such systems are not provided for under national law. |
The extension of tacit consent as proposed by the rapporteur should be approached with caution, as it is ill-suited to complex environmental and permitting procedures affecting third-party rights and public interest.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. This Chapter shall apply to procurement tenders exceeding a value of EUR 75 million. |
This paragraph establishes a proportionate monetary threshold to target large-scale strategic public procurement while avoiding administrative overhead for smaller municipal or regional tenders.
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. The planning, construction and operation of CO₂ transport and storage infrastructure as defined by Article 3, points (22) and (3), of Directive 2009/31/EC [CCS Directive], , where such infrastructure directly enables the structural reduction of nitrogen emissions from those industrial projects, shall be presumed to contribute to a long-term reduction of nitrogen emissions and shall not require an assessment of nitrogen emissions in an assessment that may be carried out to comply with Article 6(3) of Council Directive 92/43/EEC (Habitats Directive). |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. Notwithstanding point II of the Annex to the [proposal for a regulation on speeding up environmental assessment], where a project referred to in this paragraph is located in an industrial manufacturing acceleration area designated in accordance with Chapter V of this Regulation, the fact that it is subject to an environmental assessment shall not preclude the application of tacit approval to intermediate administrative stages that do not relate to either the environmental assessment itself or the final authorisation decision. |
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Dan Barna, Brigitte van den Berg, Anna-Maja Henriksson, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. The planning, construction and operation of CO₂ transport and storage infrastructure as defined by Article 3, points (22) and (3), of Directive 2009/31/EC [CCS Directive], where such infrastructure enables the structural reduction of nitrogen emissions from industrial projects, shall be presumed to contribute to a long-term reduction of nitrogen emissions and shall not require an assessment of nitrogen emissions in an assessment that may be carried out to comply with Article 6(3) of Council Directive 92/43/EEC (Habitats Directive). |
A steel plant can only switch to a cleaner process if a pipeline and storage site take away its CO2. Building that infrastructure causes small, temporary nitrogen emissions, but can still block the whole project. The Grids Package already recognises the role of CO2 infrastructure.
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. Member States shall ensure prioritised grid connection and infrastructure access for industrial decarbonisation projects, taking into account specific structural constraints of island and small connected energy systems, including cross-border interconnections, to support a just transition and energy affordability. |
This proposed new paragraph prevents grid connection bottlenecks while providing necessary legal recognition for the structural energy constraints of small, isolated, or island electricity systems.
| Text proposed by the Commission | Amendment |
|---|---|
| Article 6a | |
| Industrial projects contributing to security and defence readiness | |
| 1. Member States may identify industrial manufacturing projects that make a substantial contribution to the production, maintenance or repair of defence equipment, to military mobility, or to the resilience of critical infrastructure. The identification shall be based on a reasoned assessment by the competent national authority. | |
| 2. Projects identified pursuant to paragraph 1 shall receive priority administrative treatment within the permit-granting procedures under this Chapter. The competent authority shall coordinate the procedures and process assessments in parallel where possible. | |
| 3. This Article shall not derogate from applicable environmental, safety, export-control or security requirements and shall not affect more specific permitting rules laid down in other Union legislative acts. |
Projects that close security and defence capability gaps should receive priority administrative treatment. The amendment accelerates delivery without creating automatic exemptions from environmental, safety or security requirements.
| Text proposed by the Commission | Amendment |
|---|---|
| Article 6a | |
| Scope | |
| (1) This Chapter establishes a framework for the application of Union origin and low-carbon requirements to certain products and services from strategic sectors referred to in Annex II and III in the context of public procurement and public support schemes. | |
| (2) By [OP please insert: 2 months after entry into force] and in any event by 1 January 2028, the Commission shall adopt a delegated act providing a 3 detailed list of all the products referred to in Annex II, including the related CN and NACE codes. | |
| (3) The Commission shall conduct extensive consultation of industry and other relevant stakeholders in preparation for the adoption of the delegated act referred to in paragraph 2. |
Chapter III establishes a framework for applying Union-origin and low-carbon requirements to products of energy-intensive industries (steel, aluminium and concrete/mortar) set out in Annex II. The exact product scope remains unclear, particularly as regards more complex downstream products, such as transformers used to connect buildings to the electricity grid. To ensure legal certainty and predictable application, the Commission should define which products are covered by Annex II through a delegated act, specifying the relevant CN and NACE codes.
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| Union origin | Union origin in public procurement and other forms of public intervention |
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Sigrid Friis, Emma Wiesner, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| Union origin | Union and partner origin |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. ‘Made in Europe’ shall mean content originating in the Union or content deemed equivalent to Union origin in this Article, provided that such content contributes to genuine European value creation, including through production, processing, components, know-how, employment, skills development and integration into European value chains. To be considered made in EU a product must undergo substantive transformation in the EU, meaning that at least 75% of its added value cost comes from the EU. |
Raúl de la Hoz Quintano, Adrián Vázquez Lázara, Esteban González Pons, Pilar del Castillo Vera, Dolors Montserrat, Javier Zarzalejos, Susana Solís Pérez, Borja Giménez Larraz, Carmen Crespo Díaz, Antonio López-Istúriz White, Esther Herranz García, Nicolás Pascual de la Parte, Juan Ignacio Zoido Álvarez, Francisco José Millán Mon, Maravillas Abadía Jover, Isabel Benjumea Benjumea, Gabriel Mato
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the European Union, the European Economic Area (EEA), the European Free Trade Association (EFTA) and the United Kingdom. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, Union origin requirements refers to content originating in the Union, or, where relevant, project-tailored holistic ‘Made in EU’ criteria. |
As set out in AMs 1 and 2, the draft IAA Regulation applies a single approach—European preference rules based on NZIA components—to all industrial value chains covered by the text, despite their diversity (automotive, renewable energy, nuclear fission, hydrogen, batteries, etc.).Such a uniform approach risks oversimplifying different industrial realities and does not sufficiently reflect sector-specific characteristics or the complexity of large-scale energy infrastructure projects, which differ significantly from technologies designed for serial production. For such projects, holistic “Made in EU” criteria could instead be assessed and adapted on a project-by-project basis to better capture their contribution to the European economy. These criteria could be based on a set of macro- and microeconomic KPIs, to be further defined in the proposed Regulation and selected by the Member States, which are directly involved in delivering such large-scale projects. This amendment therefore seeks to establish the possibility of using project-specific “Made in EU” criteria as an alternative to the NZIA component-based approach, where appropriate for specific technologies.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union or in a third country in accordance with Articles 8 and 9. |
Clarification that “Union origin” refers to a broader group of countries than EU Member States alone, or alternatively, complementing the Regulation with a definition of “partner country” as currently discussed in the Council.
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union and in the members of the European Free Trade Association. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers strictly and exclusively to products manufactured in the Member States (including in OCTs). |
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Katri Kulmuni, Sigrid Friis, Anna Stürgkh, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union, the EEA and EFTA countries. |
Norway, Iceland, Liechtenstein and Switzerland are part of, or closely tied to, the internal market. Their industry is deeply integrated in Union value chains, so their content should count as Union content.
Klara Dostalova, Jaroslava Pokorná Jermanová, Tomáš Kubín, Jaroslav Bžoch, Ondřej Knotek, Jana Nagyová, Anna Bryłka, Jaroslav Knot
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the European Economic Area. |
The EEA countries (Norway, Iceland, Liechtenstein) are part of the Single Market and should not be considered third countries in the IAA. This is in line with their close integration in the EEA, their participation in the ETS and their planned involvement in the CBAM. Their inclusion among regular trading partners could weaken this long-standing partnership.
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the European Economic Area. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the European Union. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 1. For the purposes of this Chapter, content of Union origin refers to content originating in the Union. | 1. For the purposes of this Chapter, content of Union origin refers to content originating in the European Union. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. Any undertaking receiving state aid, subsidies, or other forms of direct financial assistance from the state shall, be subject to a restriction regarding dividend distributions and value transfers. |
Raúl de la Hoz Quintano, Adrián Vázquez Lázara, Esteban González Pons, Pilar del Castillo Vera, Dolors Montserrat, Javier Zarzalejos, Susana Solís Pérez, Borja Giménez Larraz, Carmen Crespo Díaz, Antonio López-Istúriz White, Esther Herranz García, Nicolás Pascual de la Parte, Juan Ignacio Zoido Álvarez, Francisco José Millán Mon, Maravillas Abadía Jover, Isabel Benjumea Benjumea, Gabriel Mato
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. For the purposes of Articles 9 and 10, the Commission shall adopt delegated acts in accordance with Article 30 by [OP: Please insert the date = six months after the date of entry into force of this Regulation] to supplement this Regulation by establishing, for products and services covered by Annex II and Annex III, the third countries or specific manufacturers from which content shall be treated as equivalent to content of Union origin, provided that all of the following criteria are met: | |
| (a) that third country provides national treatment related to Union products or entities under an agreement establishing a free trade area or a customs union, and effective reciprocity and comparable market access for Union products or economic operators are ensured in law and in practice. This shall include cases where laws, regulations or practices do not reserve public contracts for domestic products or suppliers, do not grant them a preference, do not impose local-content requirements and do not otherwise materially restrict access for Union products or economic operators; | |
| (b) inclusion of that third country does not create dependencies or other developments that may threaten the security of supply in the Union of the products in question; | |
| (c) reliable enforcement of applicable rules of origin is ensured and there is no material risk of circumvention of the Union origin requirements, including through re-export, trans-shipment or minimal processing; and | |
| (d) inclusion of that third country is not precluded by any other exception under the applicable agreement. |
Klara Dostalova, Jaroslava Pokorná Jermanová, Tomáš Kubín, Jaroslav Bžoch, Ondřej Knotek, Jana Nagyová, Jaroslav Knot, Anna Bryłka
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. The Commission shall review the definition of last substantial transformation referred to in Article 60 of Regulation (EU) No 952/2013 of the European Parliament and of the Council for products and components covered by this Chapter with the aim of including a minimum 50% of Union added value for those products and components with the aim to avoid circumvention of the rules of origin. The review shall be based on a technology- and supply-chain-specific assessment and shall not establish a horizontal minimum Union added-value requirement across all products and sectors. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. The Commission shall review the definition of last substantial transformation referred to in Article 60 of Regulation (EU) No 952/2013 of the European Parliament and of the Council for products and components covered by this Chapter with the aim of including a minimum 50% of Union added value for those products and components with the aim to avoid circumvention of the rules of origin. The review shall be based on a technology- and supply-chain-specific assessment and shall not establish a horizontal minimum Union added-value requirement across all products and sectors. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. By way of derogation for aluminium products, origin shall be determined based on the country where aluminium is first produced in liquid form via electrolysis and subsequently cast into its first solid form (smelt & cast’ rule). For the secondary production route, origin shall be determined based on the country of smelt for the primary input and the country of most recent cast for the scrap input. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. Any undertaking benefiting from public procurement procedures, public support schemes, auctions, support for investment or other direct or indirect form of public funding, support or demand-side measure under this Regulation shall comply with the requirements laid down in this Article, regardless whether this undertaking is of Union origin or from a third country. |
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Sigrid Friis, Anna Stürgkh, Emma Wiesner, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. Content of the following origin shall be equivalent to Union origin for the purposes of Articles 11, 12, 13, and 14: | |
| (a) content originating in a partner country; | |
| (b) content produced by a Strategic Project recognised under Article 6 of Regulation (EU) 2024/1252 (Critical Raw Materials Act), for the duration of that recognition. |
This paragraph sets out which content from outside the Union counts as Union content. Point (a) covers partner countries. Point (b) covers Strategic Projects under the Critical Raw Materials Act, including those outside the Union, such as in Brazil, Kazakhstan and South Africa. The Union selected them to secure its supply of critical raw materials, so one Union law should not exclude what another supports.
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Jorge Martín Frías, Hermann Tertsch, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. For the purpose of the Union origin requirements for vehicles laid down in this Chapter and in the Annex III, also a vehicle assembled in the United Kingdom shall be deemed assembled within the Union and the content originating in the United Kingdom shall be deemed to be content of Union origin. |
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Katri Kulmuni, Sigrid Friis, Anna Stürgkh, Emma Wiesner, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1b. A third country shall be deemed a partner country for all sectors listed in Annex I from the date of entry into force of this Regulation, where it: | |
| (a) meets all of the following criteria: | |
| (i) it is a party to the Agreement on Government Procurement; | |
| (ii) it has concluded or signed with the Union a customs union or an agreement establishing a free trade area, where relevant obligations of the Union exist under that agreement; | |
| (iii) it is a full member of the International Energy Agency; and | |
| (iv) it is a party to the Paris Agreement. |
Four cumulative criteria decide which countries are partners from day one: access to their public procurement (GPA), a deep trade relationship (FTA or customs union), energy and economic security (full IEA membership) and decarbonization efforts (Paris Agreement). This would countries such as the UK, Canada, Japan, South Korea and New Zealand.
| Text proposed by the Commission | Amendment |
|---|---|
| 1b. By way of derogation for steel products, components and assembled final products containing steel, only steel that has been originally melted and poured within the Union, in accordance with Regulation (EU 2026/1384), shall qualify as being of Union origin. |
Raúl de la Hoz Quintano, Adrián Vázquez Lázara, Esteban González Pons, Pilar del Castillo Vera, Dolors Montserrat, Javier Zarzalejos, Susana Solís Pérez, Borja Giménez Larraz, Carmen Crespo Díaz, Antonio López-Istúriz White, Esther Herranz García, Nicolás Pascual de la Parte, Juan Ignacio Zoido Álvarez, Francisco José Millán Mon, Maravillas Abadía Jover, Isabel Benjumea Benjumea, Gabriel Mato
| Text proposed by the Commission | Amendment |
|---|---|
| 1b. The Commission shall regularly assess whether the criteria referred to in this paragraph continue to be met. |
| Text proposed by the Commission | Amendment |
|---|---|
| 1c. By way of derogation for the purposes of this Regulation, lithium extracted in a third country may be treated as equivalent to content of Union origin where that third country is party to a comprehensive free trade agreement with the Union which provides for specific commitments concerning critical or strategic raw materials and contributes to the security and diversification of the Union’s supply of such raw materials. | |
| The Commission shall establish and regularly update the list of third countries fulfilling the conditions for the treatment of lithium as equivalent to content of Union origin laid down in the third subparagraph. |
Raúl de la Hoz Quintano, Adrián Vázquez Lázara, Esteban González Pons, Pilar del Castillo Vera, Dolors Montserrat, Javier Zarzalejos, Susana Solís Pérez, Borja Giménez Larraz, Carmen Crespo Díaz, Antonio López-Istúriz White, Esther Herranz García, Nicolás Pascual de la Parte, Juan Ignacio Zoido Álvarez, Francisco José Millán Mon, Maravillas Abadía Jover, Isabel Benjumea Benjumea, Gabriel Mato
| Text proposed by the Commission | Amendment |
|---|---|
| 1c. The Commission is empowered to adopt delegated acts in accordance with Article 30 to revoke treatment of products originating from a third country or specific manufacturers in the case of a serious breach of their commitments towards the Union or in the case of public order or economic security concerns or circumvention. |
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Sigrid Friis, Anna Stürgkh, Emma Wiesner, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1c. (b) content originating in an overseas country or territory; |
Bart Groothuis, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Sigrid Friis, Anna Stürgkh, Emma Wiesner, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1d. (c) is a Union candidate country which faces an exceptional and immediate security situation, is a party to the Agreement on Government Procurement, and has concluded with the Union an agreement establishing a free trade area, where relevant obligations of the Union exist under that agreement. |
Point (c) covers Ukraine from entry into force. The definition is drawn from the Steel Instrument (Regulation 2026/1284). Reciprocity is ensured because Ukraine is party to the GPA and has a free trade agreement with the Union that includes relevant obligations.
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Pascal Canfin, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Katri Kulmuni, Sigrid Friis, Anna Stürgkh, Emma Wiesner, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1e. The Commission shall adopt delegated acts in accordance with Article 30 to include, in whole or in part, a third country as a partner country for all sectors listed in Annex I. | |
| A third country shall be eligible for inclusion only where it is a party to the Agreement on Government Procurement, or where it has concluded with the Union a customs union or an agreement establishing a free trade area, where relevant obligations of the Union exist under that agreement. | |
| In deciding whether to include an eligible third country, the Commission shall assess the following four selection criteria: | |
| (a) whether that third country provides, de jure and de facto, effective reciprocal treatment and market access to Union products or entities across the relevant levels of government, in the sector concerned; | |
| (b) whether inclusion contributes to the diversification of Union supply chains in the sector concerned and the resilience of the Single Market and thereby contributes to the Union's economic security and energy security, in particular where Union sourcing is concentrated in a single third country. In assessing this, the Commission shall have regard to the sectoral cooperation the Union is pursuing with that country, such as a Clean Trade and Investment Partnership, a Green Alliance or a Critical Raw Materials Strategic Partnership; | |
| (c) whether inclusion of that third country creates a risk of circumvention of the Union origin requirements set out in this Regulation, in particular through the re-export of products or components originating in a third country holding more than 40% of global manufacturing capacity in the sector concerned, as well as through the establishment on its territory of undertakings, whose main purpose is to obtain access to the internal market; | |
| (d) whether that third country implements the Paris Agreement, such as through domestic carbon pricing mechanisms or measures having equivalent effect. |
After entry into force, the Commission can add further partner countries by delegated act, for all sectors or only some. A country is eligible if it is either party to the GPA, has a customs union, or has a free trade agreement or customs union with relevant obligations. So already one of these three treaties makes a third country eligible. The Commission then selects on four criteria: reciprocity, security of supply, circumvention risk and decarbonization efforts.
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Anna-Maja Henriksson, Katri Kulmuni, Sigrid Friis, Anna Stürgkh, Emma Wiesner, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1f. The Commission shall adopt delegated acts in accordance with Article 30 to exclude, in whole or in part, a third country where the criteria set out in this Article are no longer met. This shall also apply to a third country designated as partner country from entry into force of this regulation. |
A partner country loses its status when it no longer meets the criteria, for example because circumvention keeps occurring through it. This applies both to countries that qualify automatically and to those added by delegated act.
Bart Groothuis, Nikola Minchev, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Dan Barna, Barry Cowen, Billy Kelleher, Michael McNamara, Engin Eroglu, Brigitte van den Berg, Cynthia Ní Mhurchú, Anna-Maja Henriksson, Sigrid Friis, Anna Stürgkh, Karin Karlsbro, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| 1g. The first delegated act including third countries as partner countries shall be adopted within [OP: Please insert the date = 6 months after entry into force of this Regulation]. |
Trusted partners need clarity quickly. The Commission must therefore adopt the first delegated act adding partner countries within six months.
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The actual value created within the Union, in particular the manufacture and processing of components, research and development, engineering activities, skilled labour, technological know-how and value added generated within the Union, shall be taken into account for the purposes of Union origin requirements. Final assembly, packaging, finishing or other minor processing operations alone shall not be considered sufficient to establish Union origin. |
| For the purposes of this Regulation, content originating in EFTA countries, the United Kingdom and candidate countries may also be recognised as content of Union origin, provided that the country in question applies international social, labour, environmental and human rights agreements and ensures reciprocal access and genuine value creation within European value chains. | |
| No requirement relating to origin, content or the supply chain under this Regulation shall be applied in a manner contrary to requirements concerning nuclear safety, nuclear security, licensing or the qualification of suppliers under applicable Union or national law, and origin requirements relating to nuclear technologies shall not be applied until a transparent methodology for assessing and verifying compliance with them, taking into account nuclear safety, licensing and qualification of suppliers, has been adopted and is in force. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. For the purposes of the requirements laid down in this Regulation, final assembly, finishing, packaging or the last substantial transformation shall not be sufficient to demonstrate genuine European value creation where the main production steps, components, labour input, technology, know-how and value added are predominantly located outside the Union or outside third countries listed in accordance with this Article. With respect to the Union origin requirements referred to in this article and Article 11, content originating in a third country may be considered of Union origin if all the following conditions are fulfilled: |
Andrea Wechsler, Christian Ehler, Angelika Niebler, Jens Gieseke, Andreas Schwab, Norbert Herhammer, Hildegard Bentele, Markus Ferber, Oliver Schenk, Christian Doleschal, Monika Hohlmeier, Verena Mertens, Ralf Seekatz, Marie-Sophie Christ, Alexandra Mehnert, Norbert Lins, Zala Černilec Tomašič, Marion Walsmann
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. Where necessary to reflect the specific characteristics of a product, component or manufacturing process, the Commission may, by means of delegated acts and in accordance with Regulation (EU) No 952/2013, specify the processing or manufacturing operation that constitutes the relevant substantial transformation for the purposes of determining Union origin under this Regulation, including key manufacturing steps, sector- or production-route-specific rules, and processing operations which shall not, by themselves, confer a new origin. |
The amendment ensures a clear and consistent determination of Union origin based on the Union Customs Code, while allowing sector- and production-specific clarification where general origin rules do not adequately reflect complex industrial value chains. This provides legal certainty and prevents minor downstream processing from conferring origin where the key manufacturing step took place outside the Union.
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 2026/2108 establishing the Union Customs Code and the European Union Customs Authority, and repealing Regulation (EU) No 952/2013. |
| By six months after the entry into force of this Regulation, the Commission shall review the definition of last substantial, economically justified processing or working laid down in Article 169 of Regulation (EU) 2026/2108, with the aim of including at least 50% of added value originating in the Union and preventing the circumvention of the rules on the acquisition of origin. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. To be considered of Union origin, a product must undergo substantive transformation in the Union, meaning that at least 75% of its added value comes from the Union. In this sense, final assembly, finishing, packaging shall not be sufficient to demonstrate genuine European value creation. |
| This rule accounts for circular economy pathways (such as recycling) and adheres to sector-specific principles such as smelt and cast for aluminium, and melt and pour for steel. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. |
| In addition, where Union origin requirements apply to products under Annex I, point 1, point (a), such products shall be considered to be of Union origin only where the main precursors within their system boundary, representing the majority of the mass of the product, originate in the Union. |
Nicolás González Casares, Javier Moreno Sánchez, Leire Pajín, Idoia Mendia, José Cepeda, Elena Sancho Murillo, Sandra Gómez López, Lina Gálvez, Juan Fernando López Aguilar, Alicia Homs Ginel, Hana Jalloul Muro, Laura Ballarín Cereza
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Regulation (EU) 2026/2108 establishing the Union Customs Code and the European Union Customs Authority, and repealing Regulation (EU) No 952/2013 of the European Parliament and of the Council. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Regulation (EU) 2026/2108 establishing the Union Customs Code and the European Union Customs Authority, and repealing Regulation (EU) No 952/2013 of the European Parliament and of the Council. |
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Jessika van Leeuwen, Giovanni Crosetto, Nicolas Bay, Marion Maréchal
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Article 60 of Regulation (EU) No 952/2013 of the European Parliament and of the Council. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Article 169 of Regulation (EU) 2026/2108 of the European Parliament and of the Council. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 2026/2108 of the European Parliament and of the Council. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2. The origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013 of the European Parliament and of the Council. | 2. Except as provided in paragraph 3 for steel, the origin of products and components shall be determined in accordance with Regulation (EU) No 952/2013. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, Ştefan Muşoiu, Marc Angel, Bruno Tobback, Elisabeth Grossmann, Raphaël Glucksmann, Niels Fuglsang
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. By [12 months after the date of entry into force of this Regulation], the Commission shall carry out a comprehensive assessment of the adequacy of the non-preferential rules of origin for the products and components covered under this Regulation. | |
| For each product category, that assessment shall determine whether the identification of a specific production stage as constituting the last substantial transformation, a minimum share of Union value added, or a combination of both, is the most appropriate criterion to ensure that origin reflects substantial manufacturing activity and to prevent circumvention. | |
| On the basis of that assessment, the Commission shall, by [18 months after the date of entry into force of this Regulation], adopt delegated acts pursuant to Article 62 of Regulation (EU) No 952/2013 laying down binding product-specific rules for those products and components. Those delegated acts shall not lay down less stringent requirements than those set out in this Regulation. | |
| For aluminium and for products and components containing aluminium, that assessment shall in particular examine a criterion based on the place where primary aluminium is produced by electrolytic reduction and where secondary aluminium is melted and cast from waste and scrap, to the exclusion of the mere remelting or casting of imported aluminium. |
| Text proposed by the Commission | Amendment |
|---|---|
| Six years after the entry into force of this Regulation, at least three of the main specific components of the final nuclear fission technology used in a new nuclear installation, including small modular reactors, must originate in the Union or in an authorised partner country. |
| Text proposed by the Commission | Amendment |
|---|---|
| (a) the Union has concluded an agreement establishing a free trade area or a customs union, or that are parties to the Agreement on Government Procurement, where relevant obligations of the Union exist under that agreement, in relation to all the sectors listed in Annex I; |
| Text proposed by the Commission | Amendment |
|---|---|
| (b) that third country, or the economic operator operating in that third country, comply with social and labour clauses, collective bargaining, and effectively implements the ILO Fundamental Conventions, in order to promote fair competition and high-quality jobs as defined in this regulation; |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Bruno Tobback, Elisabeth Grossmann, Raphaël Glucksmann, Niels Fuglsang, Brando Benifei, Stefano Bonaccini, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| For steel products, components and assembled final products containing steel, only steel that has been originally melted, and poured within the Union, in accordance with Regulation EU 2026/1384 and Implementing Regulation (EU) 2026/1963 shall qualify as being of Union origin. |
| Text proposed by the Commission | Amendment |
|---|---|
| (c) invest in skills and training, including quality apprenticeships, and including access to training during working hours; |
| Text proposed by the Commission | Amendment |
|---|---|
| (d) take measures to reduce inequality and discrimination, pay inequalities, including the gender pay gap; |
| Text proposed by the Commission | Amendment |
|---|---|
| (e) limit subcontracting chains and prevent abusive subcontracting practices, including ensuring that the same social conditionalities apply throughout the relevant chain of contractors and subcontractors; |
| Text proposed by the Commission | Amendment |
|---|---|
| (f) the third country has a legal framework for environmental due diligence and greenhouse gas emission reporting, and complies with the commitment to implement the Paris Agreement; |
| Text proposed by the Commission | Amendment |
|---|---|
| (g) the third country protects and promotes human and labour rights, including by implementing the United Nations Global Compact and the United Nations Guiding Principles on Business and Human Rights as well as respecting international law; |
| Text proposed by the Commission | Amendment |
|---|---|
| (h) the inclusion of the third country does not entail a risk of circumvention of the Union origin requirements set out in this Regulation, in particular through the re-export of products or components originating in third countries, or through the establishment on its territory of undertakings owned and controlled by entities established in third countries that are not within the scope of this Article with the purpose to access to the Union market for such products or components. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. With respect to the Union-origin requirements referred to in Article 11, the Commission may adopt delegated acts in accordance with Article 30 in order to establish, in whole or in part, content originating in a third country with which the Union has concluded an agreement establishing a free trade area or a customs union, or are member of the WTO Government Procurement Agreement to be of Union origin if all the following conditions are fulfilled: | |
| (a) the third country has provided, in law and in practice, national treatment related to Union products or entities in relation to all contracting authorities or entities, covering all sectors listed in Annex -Ia, in the framework of the established agreement; | |
| (b) the third country has fulfilled its obligation of full and effective implementation of its agreement towards all Member States without reserve and in a non-discriminatory manner; | |
| (c) such inclusion is consistent with the objective to avoid dependencies and with the objective of strengthening the economic security of the Union, including the security of supply chains for the products in question, energy security, and the resilience of the Single Market. The third country contributes to resilience and security of Union supply chains and economic security objectives of the Union in the sectors listed in Annex -Ia. This should be assessed using the following elements: | |
| i) the level of reduction of trade dependencies via diversification of suppliers; | |
| ii) the level of integration in Union supply chains; | |
| iii) the level of investments made or planned in the Union; | |
| iv) the level of alignment with Union investment, export control and sanction policies | |
| v) the risk of circumvention as referred to in article 9a | |
| c) the third country has implemented or is preparing to implement a carbon pricing scheme comparable to the Union ETS; | |
| d) the third country upholds equivalent environmental, social and human rights standards. This should be assessed using the following criteria: | |
| i) the third country is a signatory to the Paris Agreement and is upholding its commitments under that Agreement.; and | |
| ii) the third country has ratified and implemented all fundamental ILO conventions and is committed to the ILO Declaration on Social Justice for a Fair Globalization, in particular to decent working conditions for all, wages, working hours, social protection, labour standards, skills training and gender equality. and provides effective labour protection including as regards freedom of association, collective bargaining, occupational safety and health, information and consultation of workers, equal treatment and non-discrimination | |
| iii) Protects and promotes human rights by implementing the United Nations Global Compact and the United Nations Guiding Principles on Business and Human Rights Equivalence is presumed when a third country has concluded and implemented a sanctions-based trade and sustainable development chapter with the EU. | |
| The Commission shall monitor compliance with the conditions laid down in this paragraph. Where the Commission finds, on its own initiative or following a reasoned request from the European Parliament or the Council, that those conditions are no longer met, it shall, within three months of that finding, adopt a delegated act in accordance with Article 30 to exclude a third country from any delegated act adopted pursuant to this paragraph. This delegated act should allow for a transition period of no longer than 12 months after its adoption. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Brando Benifei, Stefano Bonaccini, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. With respect to the Union-origin requirements referred to in Article 11, the Commission may adopt delegated acts in accordance with Article 30 in order to establish, in whole or in part, content originating in a third country with which the Union has concluded an agreement establishing a free trade area or a customs union, or are member of the WTO Government Procurement Agreement to be of Union origin if all the following conditions are fulfilled: | |
| (a) the third country has provided, in law and in practice, national treatment related to Union products or entities in relation to all contracting authorities or entities, covering all sectors listed in Annex -Ia; | |
| (b) such inclusion is consistent with the objective to avoid dependencies and with the objective of strengthening the economic security of the Union, including the security of supply chains for the products in question, energy security, and the resilience of the Single Market. The third country contributes to resilience and security of Union supply chains and economic security objectives of the Union in the sectors listed in Annex -Ia. This should be assessed using the following elements: | |
| i) the level of reduction of trade dependencies via diversification of suppliers ; | |
| ii) the level of integration in Union supply chains ; | |
| iii) the level of investments made or planned in the Union; | |
| iv) the level of alignment with Union investment, export control and sanction policies | |
| v) the risk of circumvention as referred to in article 9a | |
| c) the third country has implemented or is preparing to implement a carbon pricing scheme comparable to the Union ETS; | |
| d) the third country upholds equivalent environmental, social and human rights standards. This should be assessed using the following criteria: | |
| i) the third country is a signatory to the Paris Agreement and is upholding its commitments under that Agreement.; and | |
| ii) the third country has ratified and implemented all fundamental ILO conventions and is committed to the ILO Declaration on Social Justice for a Fair Globalization, in particular to decent working conditions for all, wages, working hours, social protection, labour standards, skills training and gender equality. and provides effective labour protection including as regards freedom of association, collective bargaining, occupational safety and health, information and consultation of workers, equal treatment and non-discrimination | |
| iii) Protects and promotes human rights by implementing the United Nations Global Compact and the United Nations Guiding Principles on Business and Human Rights | |
| Equivalence is presumed when a third country has concluded and implemented a sanctions-based trade and sustainable development chapter with the EU. | |
| The Commission shall monitor compliance with the conditions laid down in this paragraph. Where the Commission finds, on its own initiative or following a reasoned request from the European Parliament or the Council, that those conditions are no longer met, it shall, within three months of that finding, adopt a delegated act in accordance with Article 30 to exclude a third country from any delegated act adopted pursuant to this paragraph. This delegated act should allow for a transition period of no longer than 12 months after its adoption. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. With respect to the Union-origin requirements referred to in Articles 11, 12 and 13, the Commission shall adopt delegated acts in accordance with Article 30 to recognise, in whole or in part, content originating in a third country as being of Union origin if all the following conditions are fulfilled: | |
| (a) the third country has provided, in law and in practice, national treatment related to Union products or entities under agreements establishing a free trade area or a customs union or the Agreement on Government Procurement, in relation to all the sectors listed in Annex I; | |
| (b) such inclusion is consistent with the objective to avoid dependencies and with the objective of strengthening the economic security of the Union, including the security of supply chains for the products in question, energy security, and the resilience of the Single Market; | |
| (c) the recognition does not create a significant risk of distortions of competition in the Union market arising from subsidies or other forms of state support granted by the third country in respect of the products concerned; | |
| (d) the third country complies with the commitment to implement the Paris Agreement through its nationally determined contributions; | |
| (e) where the third country has established, or is planning to establish, demand-side measures for low-carbon industrial products or public support schemes comparable to those referred to in Article 12, those measures or schemes provide, in law and in practice, national treatment to Union products or entities; | |
| (f) the inclusion of the third country does not entail a risk of circumvention of the Union origin requirements set out in this Regulation, in particular through the re-export of products or components originating in third countries which are not contained in a delegated act adopted based on this Article, or through the establishment on its territory of undertakings owned and controlled by entities established in third countries that are not within the scope of this Article with the purpose to access to the Union market for such products or components. | |
| Where the above conditions are no longer met, the Commission shall adopt a delegated act in accordance with Article 30 to exclude in whole or in part a third country from any delegated act adopted on this paragraph. | |
| For third countries meeting all of the following criteria, the Commission shall adopt the delegated acts referred to in the first subparagraph no later than three months after the date of entry into force of this Regulation, provided that the conditions set out in points (a) to (f) are fulfilled: | |
| (i) it is a party to the Agreement on Government Procurement; | |
| (ii) it has concluded or signed with the Union an agreement establishing a free trade area or a customs union, where relevant obligations of the Union exist under that agreement; | |
| (iii) it is a full member of the International Energy Agency; | |
| and (iv) it is a party to the Paris Agreement. |
This amendment makes the recognition of third-country content as being of Union origin subject to clear conditions safeguarding reciprocity, fair competition, the Union’s economic security and climate commitments, while preventing circumvention. It extends this approach to both public procurement under Article 11 and public support schemes under Article 12, requiring national treatment for Union products or entities where comparable measures or schemes exist in the third country. Recognition must be withdrawn where the conditions are no longer met. For third countries meeting the additional criteria set out in points (i) to (iv), the amendment establishes a binding three-month deadline for the adoption of the relevant delegated acts, provided that all substantive conditions are fulfilled. This provides predictability for trading partners and businesses and supports timely implementation without weakening the safeguards governing eligibility.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. With a view to ensuring that the requirements laid down in this Regulation are commensurate with the industrial capacity available in the Union, an ex-ante verification mechanism shall be established to assess the availability of Union industrial capacity before any new mandatory requirement concerning Union origin or low-carbon content becomes applicable. That mechanism shall also regularly monitor the development of Union industrial capacity, with a view to determining whether any adjustments to the applicable requirements are necessary and, where appropriate, enabling such adjustments to be introduced. For each product, material or component concerned, the mechanism shall assess at least: | |
| (a) the current production capacity available within the Union; | |
| (b) the number of suppliers established and operating within the Union; | |
| (c) the price differential compared with equivalent alternatives available on international markets; | |
| (d) the quality of the product and its compliance with applicable technical and certification requirements; | |
| (e) the impact on SMEs, downstream undertakings and exporting undertakings; and | |
| (f) the risk of creating or reinforcing strategic dependencies, whether within or outside the Union. | |
| The information gathered via this mechanism shall be used for the subsequent specification of different minimum percentages of Union content, taking into account both the geographical scope used to determine Union origin and the products, materials or components to which those percentages apply. |
It is considered appropriate to introduce a mechanism ensuring that the European content requirements laid down in the IAA are aligned with the EU’s industrial capacity, to avoid a mismatch between policy objectives and available manufacturing capacity. Bringing the different requirements into force before a competitive supply base is in place could have the opposite effect. Accordingly, the minimum thresholds should not create bottlenecks or disproportionate cost increases that could undermine project competitiveness. The targets should be phased in progressively in line with European production capacity, which should be monitored in advance and strengthened through policies supporting investment and industrial development. To that end, a mechanism shall be established to assess developments concerning each product, material or component falling within the scope of the IAA and, where necessary, to adjust the applicable Union-content percentages. Such adjustment may also take the form of allocating the required percentages across different geographical tiers, comprising the Union, the European Economic Area and third countries that grant reciprocal market access to Union products and comply with quality, environmental and labour standards equivalent to those applicable in the Union
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. By way of derogation from paragraph 3, until [OP: please insert the date = 6 years after the date of entry into force of this Regulation], steel which has obtained Union origin in accordance with paragraph 2 shall be considered to be of Union origin where the last substantial transformation conferring that origin took place in an installation which fulfils all of the following conditions: | |
| (a) the installation is located in the Union and is operated by an undertaking established in the Union; | |
| (b) on 4 March 2026, the installation was carrying out activities classified under NACE Rev. 2 group 24.1, 24.2 or 24.3. The first subparagraph shall apply without prejudice to restrictive measures adopted under Article 215 TFEU. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The determination of origin shall not be circumvented through minimal processing or assembly operations that do not confer origin under Regulation (EU) No 952/2013. Compliance checks shall, where relevant, cover the origin of components subject to a specific requirement under this Regulation and shall use existing customs and product documentation wherever possible. For steel, available information identifying the country where it was first melted and poured shall be used for verification where relevant and proportionate, without replacing the applicable origin rules or the equivalent treatment provided for in Articles 8 and 9. The same evidence shall not be requested again where it is already lawfully available to the competent authority. |
European-origin requirements must reward genuine manufacturing rather than superficial assembly. Melt-and-pour evidence can support proportionate verification without replacing origin rules, disrupting partner equivalence or duplicating documentation.
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Notwithstanding paragraph 2, and solely for the purposes of this Regulation, a product or component shall be considered to be of Union origin only if it meets both of the following conditions: | |
| (a) it underwent its last substantial processing in the EU, within the meaning of Article 60 of Regulation (EU) No 952/2013; | |
| (b) the value added represents at least 60 % of the ex-works price, calculated in accordance with the definition provided in Article 3 of this Regulation. | |
| Operations involving a minor transformation, and therefore not in accordance with Article 3, shall not be sufficient to confer Union origin under this Regulation, regardless of their contribution to Union added value. |
Pierre Jouvet, Raphaël Glucksmann, Nora Mebarek, Jean-Marc Germain, François Kalfon, Christophe Clergeau
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. For the purposes of this Chapter, products and components shall be treated as content of Union origin if they are wholly obtained in an overseas country or territory listed in Annex I to Council Decision (EU) 2021/1764, or if they are manufactured there exclusively from materials of local or Union origin, provided that: | |
| (a) the installation is not controlled by an entity established in a third country referred to in Article 11(1); | |
| (b) the applicable social, labour and environmental law, and the fundamental conventions of the International Labour Organisation, are complied with. | |
| This treatment shall be without prejudice to Union customs legislation. |
Overseas countries and territories are part of Member States and are not third countries. This treatment is limited to local resources and the processing of those resources locally with a view to supporting local employment and preventing the territories concerned, which are located outside the customs territory, from being used to circumvent the origin requirements.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Project-tailored holistic “Made in EU” criteria should encompass: | |
| (a) The ownership and control of Intellectual Property (IP) rights associated with components and sub-components; | |
| (b) The European location of manufacturing and processing operations for sub-components; | |
| (c) The local workforce used for the manufacturing/assembly of the final component/subcomponent; | |
| (d) Gross Value Added in the EU; | |
| (e) The location of long-term maintenance and service contracts in the EU. | |
| When implementing major infrastructure projects related to certain technologies (as defined in Annex II to Regulation (EU) 2024/1735), Member States shall monitor these performance indicators. |
The present amendment seeks to supplement Article 7(1), as amended, by introducing a specific paragraph on holistic “Made in EU” criteria for certifying European origin in relation to certain technologies used in large-scale infrastructure projects. Responsibility for monitoring compliance with these criteria would lie with the Member States, which are directly involved in their delivery through public procurement, State aid and other instruments. This would allow them to assess the appropriate level of ambition on a project-by-project basis, taking into account the specific characteristics and assets of the local nuclear ecosystem.
João Cotrim De Figueiredo, Yvan Verougstraete, Morten Løkkegaard, Dan Barna, Engin Eroglu, Bart Groothuis, Jeannette Baljeu
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall maintain a single, publicly accessible and regularly updated electronic list of third countries, sectors and product categories in respect of which content is treated as equivalent to Union origin under this Regulation. The list shall clearly identify the date from which such treatment applies and any sectoral or product-specific limitation. Economic operators may rely on such treatment by identifying the relevant content and country in the self-declaration or equivalent document used for the purposes of this Regulation. No prior individual authorisation or additional application shall be required where the applicable conditions are met. |
Make partner-country treatment genuinely easy to opt into. A company should be able to check one authoritative list, identify the relevant content in its existing declaration and rely on the rule. It should not be necessary to interpret several delegated acts or apply separately for equivalent-origin treatment.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Union origin requirements and third-country equivalence rules laid down in this Chapter shall be applied in accordance with the Union's obligations under WTO agreements and international agreements concluded by the Union. The Commission shall regularly assess compliance of the implementation of this Chapter with those obligations. It shall report its findings to the European Parliament and the Council. The Commission shall publish and keep data guidance on the relevant coverage of those obligations. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Union origin requirements do not apply to projects for which an auction has been announced, a support scheme was established or the application for support was submitted before the date on which the relevant requirement under Annex II came into effect, even if the procurement of the final product or its main specific components takes place after that date. The update of an existing support scheme shall result in the application of the new requirements only if it alters the eligibility conditions for the final products receiving support. |
Nicolás González Casares, Javier Moreno Sánchez, Leire Pajín, Idoia Mendia, José Cepeda, Elena Sancho Murillo, Sandra Gómez López, Lina Gálvez, Juan Fernando López Aguilar, Alicia Homs Ginel, Hana Jalloul Muro, Laura Ballarín Cereza
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. By six months after the entry into force of this Regulation, the Commission shall review the definition of last substantial, economically justified processing or working laid down in Article 169 of Regulation (EU) 2026/2108 for products and components covered by this chapter with the aim of including at least 50% of added value originating in the Union for those products and components and preventing the circumvention of the rules on the acquisition of origin. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall review the application, to products and components covered by this Regulation, of the rules determining the last substantial transformation referred to in f Regulation (EU) No 2026/2108, with a view to preventing circumvention of the Union origin requirements laid down in this Regulation and ensuring genuine value creation within the Union, while taking into account the specific characteristics and realities of the relevant supply chains. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. By way of derogation for aluminium products, origin shall be determined based on the country where aluminium is first produced in liquid form via electrolysis and subsequently cast into its first solid form (smelt & cast rule). For the secondary production route, origin shall be determined based on the country of smelt for the primary input and the country of most recent cast for the scrap input. |
For steel, the current definition using Regulation (EU) No 2013/952 cannot apply, as its ‘last substantial transformation’ rule would undermine the objective by allowing third-country steel to gain Union origin status through minor downstream processing. Such a loophole would risk diverting decarbonisation investments away from Europe and rewarding imports of partly finished products instead of supporting genuine EU -based production. A steel melt and pour requirement is necessary as an additional criterion in Article 7 to ensure that the objectives of the IAA are being met i.e. growing industry within the EU, securing EU resilience, strategic autonomy, economic security and public order. In particular, the Union Origin definition of Article 7 is relevant in the context of the Low-Carbon Steel Credit made in the EU under the CO2 standards of cars and vans. Therefore, it is about strengthening the automotive value-chain in the EU. Referencing the “melt and pour” definition adopted in Regulation EU 2025/0726 ensures regulatory coherence. Moreover, it makes sure that the major steelmaking processes and decarbonisation takes place in the EU, and therefore ensures a lead market demand that recognises EU investments. Article 7.2 refers to Products and Components, which confirms the intention to cover all made of steel products.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall review the definition of the last substantial transformation referred in Article 60 of Regulation (EU) No 952/2013 of the European Parliament and of the Council for products and components covered by this Chapter with the aim of including a minimum 50% of Union added value for those products and components with the aim to avoid circumvention of the rules of origin. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall review the definition of the last substantial transformation referred in Article 60 of Regulation (EU) No 952/2013 of the European Parliament and of the Council for products and components covered by this Chapter with the aim of including a minimum 50% of Union added value for those products and components with the aim to avoid circumvention of the rules of origin. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall review the definition of the last substantial transformation referred in Article 60 of Regulation (EU) No 952/2013 of the European Parliament and of the Council for products and components covered by this Chapter with the aim of including a minimum 50% of Union added value for those products and components with the aim to avoid circumvention of the rules of origin. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Union origin and low-carbon requirements laid down in this Chapter shall only apply at the point of the procurement procedure or awarding of support under Articles 11 and 12. They shall not restrict the lawful use of spare parts and components that do not comply with the relevant Union origin and low-carbon requirements during the vehicle's or product's lifetime. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Union origin requirements referred to in this Chapter should not preclude contracting authorities and contracting entities in Ireland from allowing tenders submitted by economic operators established in the North of Ireland to access procurement procedures, in recognition of the all-island dimension of Ireland's economy. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall review the definition of the last substantial transformation referred in Article 60 of Regulation (EU) No 952/2013 of the European Parliament and of the Council for products and components covered by this Regulation with the aim to avoid circumvention of the rules of origin. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. For steel products, steel components and products containing steel, only steel originally melted and poured within the Union shall qualify as content of Union origin. Subsequent processing or transformation shall not alter the origin of the steel for the purposes of this Chapter. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The Commission shall ensure that compliance mechanisms related to Union origin requirements remain proportionate to the size, resources and administrative capacity of SMEs. Standardised declaration templates and digital tools should be made available to facilitate compliance. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. By way of derogation from paragraph 2, for steel products, components and assembled final products containing steel only steel that has been originally melted and poured in the Union, in accordance with Regulation 2026/1384, shall qualify as of Union origin. |
Union Custom code referred to in par. 2, the origin of a product is determined based on the last substantial transformation carried out in the Union. For steel products, Union origin may therefore be conferred on imported semi-finished products even though the upstream carbon intensive production processes have taken place outside the Union. Art. 7 must clearly stipulate that only steel originally melted and poured in the Union can qualify as Union origin.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. In evaluating compliance with Union origin requirements, specific account shall be taken of the structural constraints faced by small island Member States, including reliance on imported raw materials and intermediate inputs required for local manufacturing. |
Origin-verification rules should account for the higher costs faced by small island economies. While the EU-wide estimate is around EUR 19 per resident, the indicative additional cost for these economies is EUR 64–94 per resident. They rely heavily on imported materials and technology, but benefit less directly from the manufacturing gains included in the Commission’s assessment. The rules should reflect this imbalance to avoid putting them at a disadvantage in the single market.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. Where the above conditions are not met, the Commission, Member State, contracting authority or contracting entity shall exclude the third country, or the economic operator operating in that third country, from benefitting from this regulation. |
Paolo Borchia, Isabella Tovaglieri, Raffaele Stancanelli, Jorge Martín Frías, Hermann Tertsch, Anna Bryłka, Klara Dostalova, Jana Nagyová, Ondřej Knotek, Jaroslav Bžoch, Tomáš Kubín
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. For steel products and components containing steel, only steel originally melted and pour within the Union, on the basis of the "melt and pour" principle as defined under the Regulation (EU) 2026/1384, shall qualify as being of Union origin. |
Mariateresa Vivaldini, Daniele Polato, Carlo Fidanza, Elena Donazzan, Nicola Procaccini, Sergio Berlato, Stefano Cavedagna, Carlo Ciccioli, Alessandro Ciriani, Pietro Fiocchi, Alberico Gambino, Chiara Gemma, Paolo Inselvini, Lara Magoni, Mario Mantovani, Giuseppe Milazzo, Denis Nesci, Michele Picaro, Ruggero Razza, Antonella Sberna, Marco Squarta, Francesco Torselli, Francesco Ventola, Giovanni Crosetto, Nicolas Bay, Marion Maréchal
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. For steel products, components and assembled final products containing steel, only steel that has been originally melted and poured within the Union, in accordance with Regulation (EU 2026/1384), shall qualify as being of Union origin. |
For steel, the current definition using Regulation (EU) No 2013/952 cannot apply, as its ‘last substantial transformation’ rule would undermine the objective by allowing third-country steel to gain Union origin status through minor downstream processing. Such a loophole would risk diverting decarbonisation investments away from Europe and rewarding imports of partly finished products instead of supporting genuine EU -based production. The “melt and pour” criteria adopted in Regulation EU 2025/0726 ensures that the major steelmaking processes and decarbonisation takes place in the EU, and therefore ensures a lead market demand that recognises EU investments.
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. For steel products and components containing steel, only steel originally melted and poured within the Union shall qualify as Union origin product. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. With respect to the Union-origin requirements referred to in Article 11, the Commission may adopt delegated acts in accordance with Article 30 in order to establish, in whole or in part, content originating in a third country to be of Union origin if all the following conditions are fulfilled: | |
| (a) the third country has provided, in law and in practice, national treatment related to Union products or entities under agreements establishing a free trade area or a customs union or the Agreement on Government Procurement, in relation to all the sectors listed in Annexes II and III regarding public procurement and public support schemes; | |
| (b) such inclusion is consistent with the objective to avoid dependencies and with the objective of strengthening the economic security of the Union, including the security of supply chains for the products in question, energy security, and the resilience of the Single Market; | |
| (c) the third country has a legal framework for competition that is substantially equivalent to that applying in the Union single market, including in respect to environmental due diligence and greenhouse gas emission reporting, and has ratified and effectively implements the ILO Fundamental Conventions; | |
| (d) the third country complies with the commitment to implement the Paris Agreement through its national determined contributions and implements domestic carbon prices mechanisms or measures having equivalent effects; | |
| (e) the third country protects and promotes human rights by implementing the United Nations Global Compact and the United Nations Guiding Principles on Business and Human Rights, abide by rules and standards equivalent to OECD Due diligence guidance for responsible business conduct, in particular the guidelines related to combatting corruption, the OECD due diligence guidance for responsible supply chains of minerals from conflict-affected and high-risk areas, and the OECD Due Diligence Guidance for Meaningful Stakeholder Engagement in the Extractive Sector, including where referring to the principles set out in the United Nations Declaration on the Rights of Indigenous Peoples ; | |
| (f)the third country has established, or is committed to establishing within a defined timeframe, demand-side measures for low-carbon industrial products comparable to those provided for in this Regulation and which provide national treatment to Union products or entities; | |
| (g) the inclusion of the third country does not entail a risk of circumvention of the Union origin requirements set out in this Regulation, in particular through the re-export of products or components originating in third countries which are not contained in a delegated act adopted based on this Article, or through the establishment on its territory of undertakings owned and controlled by entities established in third countries which are not contained in a delegated act adopted based on this Article with the purpose to access to the Union market for such products or components. | |
| The Commission shall regularly monitor with a view to assessing whether the third countries still meet the conditions listed under this Regulation. This monitoring exercise shall take place at least once a year. | |
| Where the above conditions are no longer met, the Commission shall adopt a delegated act in accordance with Article 30 to exclude in whole or in part a third country from any delegated act adopted on this paragraph. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. With respect to the Union-origin requirements referred to in Article 11, the Commission may adopt delegated acts in accordance with Article 30 in order to establish, in whole or in part, content originating in a third country to be of Union origin if all the following conditions are fulfilled: | |
| (a) the third country has provided, in law and in practice, national treatment related to Union products or entities under agreements establishing a free trade area or a customs union or the Agreement on Government Procurement, in relation to all the sectors listed in Annex I; | |
| (b) such inclusion is consistent with the objective to avoid dependencies and with the objective of strengthening the economic security of the Union, including the security of supply chains for the products in question, energy security, and the resilience of the Single Market; | |
| (c) the third country has a legal framework for competition that is substantially equivalent to that applying in the Union single market, including in respect to environmental due diligence and greenhouse gas emission reporting, and has ratified and effectively implements the ILO Fundamental Conventions; | |
| (d) the third country complies with the commitment to implement the Paris Agreement through its national determined contributions and implements domestic carbon prices mechanisms or measures having equivalent effects; | |
| (e) the third country protects and promotes human rights by implementing the United Nations Global Compact and the United Nations Guiding Principles on Business and Human Rights; | |
| (f) the third country has established, or is committed to establishing within a defined timeframe, demand-side measures for low-carbon industrial products comparable to those provided for in this Regulation and which provide national treatment to Union products or entities; | |
| (g) the inclusion of the third country does not entail a risk of circumvention of the Union origin requirements set out in this Regulation, in particular through the re-export of products or components originating in third countries which are not contained in a delegated act adopted based on this Article, or through the establishment on its territory of undertakings owned and controlled by entities established in third countries that are not within the scope of this Article with the purpose to access to the Union market for such products or components. | |
| Where the above conditions are no longer met, the Commission shall adopt a delegated act in accordance with Article 30 to exclude in whole or in part a third country from any delegated act adopted on this paragraph. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. With respect to the Union-origin requirements referred to in Article 11, the Commission may adopt delegated acts in accordance with Article 30 in order to establish, in whole or in part, content originating in a third country to be of Union origin if all the following conditions are fulfilled: (a) the third country has provided, in law and in practice, national treatment related to Union products or entities under agreements establishing a free trade area or a customs union or the Agreement on Government Procurement, in relation to all the sectors listed in Annex I; (b) such inclusion is consistent with the objective to avoid dependencies and with the objective of strengthening the economic security of the Union, including the security of supply chains for the products in question, energy security, and the resilience of the Single Market; (c) the third country has a legal framework for competition that is substantially equivalent to that applying in the Union single market, including in respect to environmental due diligence and greenhouse gas emission reporting, and has ratified and effectively implements the ILO Fundamental Conventions; (d) the third country complies with the commitment to implement the Paris Agreement through its national determined contributions and implements domestic carbon prices mechanisms or measures having equivalent effects; (e) the third country protects and promotes human rights by implementing the United Nations Global Compact and the United Nations Guiding Principles on Business and Human Rights; (f) the third country has established, or is committed to establishing within a defined timeframe, demand-side measures for low-carbon industrial products comparable to those provided for in this Regulation and which provide national treatment to Union products or entities; (g) the inclusion of the third country does not entail a risk of circumvention of the Union origin requirements set out in this Regulation, in particular through the re-export of products or components originating in third countries which are not contained in a delegated act adopted based on this Article, or through the establishment on its territory of undertakings owned and controlled by entities established in third countries that are not within the scope of this Article with the purpose to access to the Union market for such products or components. Where the above conditions are no longer met, the Commission shall adopt a delegated act in accordance with Article 30 to exclude in whole or in part a third country from any delegated act adopted on this paragraph. |
Nicolás González Casares, Javier Moreno Sánchez, Leire Pajín, Idoia Mendia, José Cepeda, Elena Sancho Murillo, Sandra Gómez López, Lina Gálvez, Juan Fernando López Aguilar, Alicia Homs Ginel, Hana Jalloul Muro, Laura Ballarín Cereza
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. Pending the development and implementation of more advanced frameworks for political and economic association with the Union, the competent authorities and the Commission shall endeavour to grant the most favourable treatment and the most flexible application of the provisions of this Chapter to products, services and investments originating in third countries which already have associations or trade agreements with the Union, which are part of a customs union with the Union or which belong to the European Economic Area. That treatment shall apply in particular during the transitional period prior to the entry into force of the acts referred to in this Article, in order to preserve the economic integration and continuity of strategic value chains with those partners. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. Where severe supply chain disruptions, market availability limits, or disproportionate compliance costs impact small island economies, Member States may grant temporary derogations or apply flexible origin-calculation rules to ensure local industries are not excluded from enabling measures under this Chapter. |
Small manufacturers in island economies should not lose access to industrial support because supply disruptions, limited suppliers or high transport costs make origin requirements harder to meet. Temporary derogations or flexible origin calculations would protect local production and investment where compliance is excessively costly or impractical. Such measures would apply only where objectively justified, for as long as necessary, without undermining the EU’s origin objectives.
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. For the purposes of paragraph 2, a tyre shall be considered to be of EU origin where it has been vulcanised in the Union. A retreaded tyre shall be considered to be of EU origin when the retreading, including the vulcanisation of the new tread, has been carried out in the Union. |
Vulcanisation is the industrial process that gives the tyre its essential characteristics. Making this the criterion for origin – in accordance with the rules based on sufficient processing used in trade agreements – provides a workable, verifiable and easily monitored rule, given that some raw materials, such as natural rubber, cannot be produced within the Union.
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. Where that review identifies a risk of circumvention or finds that the applicable rules do not ensure genuine value creation within the Union for specific products or components, the Commission shall take appropriate action in accordance with the relevant provisions of Regulation (EU) No 2026/2108. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. By way of derogation from any delegated acts adopted based on paragraph 2b, with respect to the Union origin requirements referred to in Article 12, content of Union origin refers to content originating in the Union pursuant to paragraphs 1 and 2 of this Article. |
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. The Union origin conditions applicable to products and components under this Regulation shall be assessed on the basis of the cumulative conditions laid down in paragraph 2a. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2b. For the purposes of this Regulation, metal products shall be deemed to originate in the Union where they have been melted and cast in the Union. |
For the metal sector, the mandatory introduction of a “melted and poured” requirement is essential to prevent any circumvention of the rules of origin, as steelmaking constitutes the central and defining stage of the production process from both an industrial and an environmental perspective.
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| 2c. By way of exception, critical raw materials, industrial resources and essential inputs for the value chains covered by this Regulation that originate in an eligible overseas country or territory within the meaning of Article 3, point 40b, shall be treated as content of Union origin. The origin of those materials, resources and inputs shall be determined in accordance with the rules applicable under Council Decision (EU) 2021/1764. | |
| This treatment shall be subject to the condition that their extraction, processing or production complies with appropriate requirements relating to the protection of biodiversity, water management, pollution prevention, waste treatment and environmental traceability. | |
| It shall be strictly limited to the materials, resources and inputs referred to in the first subparagraph and shall not confer on the products concerned non-preferential Union origin within the meaning of Regulation (EU) No 952/2013. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2c. When assessing countries’ applications under the ‘opt-in’ procedure, the Commission shall give priority to European countries, in line with the European dimension of the Union as reflected in the Treaties, in particular Article 49 of the Treaty on European Union, and taking into account the extent to which the countries concerned are integrated into the Union’s value chains. This applies in particular to the countries of the European Economic Area and the European Free Trade Association, the United Kingdom and the candidate countries with which accession negotiations are actively being conducted. For candidate countries, eligibility for this priority is subject to a rate of alignment in excess of at least 80 % with declarations and decisions relating to the Common Foreign and Security Policy, as indicated in the Commission’s latest annual report on enlargement. |
The transition from automatic equivalence to recognition on request must not penalise the European partners that are most closely integrated into the internal market. This amendment enshrines in the enacting terms the objective of progressive integration of candidate countries into the Union’s value chains, as set out in recital 17. It establishes a hierarchy based on Article 49 TEU and on an objective criterion of economic integration.
| Text proposed by the Commission | Amendment |
|---|---|
| 2c. When applying paragraph 2b, the Commission shall give priority to European countries, in line with the European dimension of the Union as reflected in the Treaties, in particular Article 49 of the Treaty on European Union, and if necessary for taking into account the integration of those countries in Union value chains, in particular the countries of the EEA, EFTA and the United Kingdom. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, Javier Moreno Sánchez, Nicolás González Casares, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, José Cepeda, Hana Jalloul Muro, Idoia Mendia, Ştefan Muşoiu, Marc Angel, Elena Sancho Murillo, Bruno Tobback, Elisabeth Grossmann, Laura Ballarín Cereza, Raphaël Glucksmann, Niels Fuglsang, Brando Benifei, Stefano Bonaccini, Lina Gálvez
| Text proposed by the Commission | Amendment |
|---|---|
| 2c. When applying paragraph 2b, the Commission shall give priority to European countries, in line with the European dimension of the Union as reflected in the Treaties, in particular Article 49 of the Treaty on European Union, and if necessary for taking into account the integration of those countries in Union value chains, in particular the countries of the EEA, EFTA and the United Kingdom. |
Nicolás González Casares, Javier Moreno Sánchez, Leire Pajín, Idoia Mendia, José Cepeda, Elena Sancho Murillo, Sandra Gómez López, Lina Gálvez, Juan Fernando López Aguilar, Alicia Homs Ginel, Hana Jalloul Muro, Laura Ballarín Cereza
| Text proposed by the Commission | Amendment |
|---|---|
| 2c. Steel products and components shall be considered to be of Union origin where the steel used in their manufacture has been originally melted and poured within the Union, in accordance with Regulation (EU) 2026/1384, Regulation (EU) 2026/1963 and any implementing, delegated or other acts adopted pursuant to those regulations. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2c. By way of derogation from any delegated acts adopted based on paragraph 2b, with respect to the Union origin requirements referred to in Article 12, content of Union origin refers to content originating in the Union pursuant to paragraphs 1 and 2 of this Article. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2c. By way of derogation from any delegated acts adopted based on paragraph 2b, with respect to the Union origin requirements referred to in Article 12, content of Union origin refers to content originating in the Union pursuant to paragraphs 1 and 2 of this Article. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2d. The Commission shall annually publish a report and present it to the European Parliament and Council about the implementation of this Article. This report shall provide for an analysis of the market situation, and an overview of their activities regarding adoption or non-adoption of delegated acts. | |
| The report shall also assess whether further conditionalities, in particular with regard to climate, environmental and social standards, are needed to ensure a level playing-field. | |
| The European Parliament through its competent committees may provide an opinion on the report by the Commission to outline its position. |
| Text proposed by the Commission | Amendment |
|---|---|
| 2d. When applying paragraph 2b, the Commission shall give priority to European countries, in line with the European dimension of the Union as reflected in the Treaties, in particular Article 49 of the Treaty on European Union, and if necessary for taking into account the integration of those countries in Union value chains, in particular the countries of the EEA, EFTA and the United Kingdom. |
Bart Groothuis, Nikola Minchev, Christophe Grudler, Jeannette Baljeu, Morten Løkkegaard, Barry Andrews, Sandro Gozi, Pascal Canfin, Sophie Wilmès, Benoit Cassart, Yvan Verougstraete, Brigitte van den Berg, Anna-Maja Henriksson, Sigrid Friis, Karin Karlsbro, Martin Hojsík, Ľubica Karvašová, Ivars Ijabs
| Text proposed by the Commission | Amendment |
|---|---|
| Article 7a | |
| Anti-circumvention of Union origin | |
| 1. Content originating from partner countries shall not be considered to be of Union origin, where circumvention exists. Circumvention exists where either of the following applies: | |
| (a) the content is produced by an economic operator owned or controlled by a natural or legal person from a third country which holds more than 40% of global manufacturing capacity in the sector concerned; | |
| (b) more than 50% of the value of the parts of the product originates in a third country which holds more than 40% of global manufacturing capacity in the sector concerned. | |
| Ownership and control shall be assessed at the level of the beneficial owner at the end of the ownership chain, including where exercised indirectly through any person or undertaking acting on behalf of or at the direction of that owner. Control shall be presumed where such persons hold, individually or collectively, 25% or more of the share capital or voting rights of the operator concerned, or of the assets used to produce the content. | |
| 2. An economic operator offering content as equivalent to Union origin shall carry out a self-assessment to determine whether the content is subject to circumvention. On that basis it shall submit a self-declaration. The Commission shall adopt implementing acts laying down the standard form of that declaration, in accordance with the examination procedure referred to in Article 31(2). | |
| 3. Where circumvention by an economic operator is established on a second or any subsequent occasion within three years, that economic operator and any undertaking controlled by the same beneficial owner shall be excluded from any procedure or support covered by this Regulation for a period of between one and three years. |
Partner content must not become a back door around the origin rules. Think of a battery plant in a partner country, owned by a company from a country that dominates global production. Companies offering partner content check this themselves in one standard form. A company caught twice with a false declaration within three years is excluded for one to three years. The 50% threshold is the same single-country cap the Commission already uses in the NZIA.
Julie Rechagneux, Aleksandar Nikolic, Mathilde Androuët, Virginie Joron, Christophe Bay, Thierry Mariani, Mélanie Disdier
| Text proposed by the Commission | Amendment |
|---|---|
| Article 7a | |
| Economic security | |
| 1. The strategic sectors and technologies covered by this Regulation are essential for protecting the Union’s economic security and safeguarding its essential security interests within the meaning of Article XXI of the General Agreement on Tariffs and Trade and Article III of the WTO Agreement on Government Procurement. | |
| 2. For the purposes of public procurement procedures, public support schemes, auctions and other forms of public intervention falling within the scope of this Regulation, and in relation to products, components or technologies, the Union hereby invokes the security exceptions referred to in paragraph 1. | |
| 3. In respect of the procedures and forms of intervention referred to in paragraph 2, content originating in third countries shall not be regarded as being of Union origin and shall not be treated as content of Union origin for the purposes of this Regulation. By way of an exception, critical raw materials, industrial resources and strategic inputs originating in an overseas country or territory listed in Annex II to the Treaty on the Functioning of the European Union may be treated as provided for in Article 7(2c), subject to the conditions laid down in that provision. | |
| 4. Notification of the invocation of the security exceptions referred to in paragraph 2 shall be provided to the relevant WTO bodies in accordance with the applicable procedures. The recitals to this Regulation set out the security justification for each sector and technology. |
Pierre Jouvet, Kathleen Van Brempt, Jens Geier, François Kalfon, René Repasi, Jean-Marc Germain, Matthias Ecke, Ştefan Muşoiu, Marc Angel, Bruno Tobback, Elisabeth Grossmann, Christophe Clergeau, Raphaël Glucksmann, Niels Fuglsang
| Text proposed by the Commission | Amendment |
|---|---|
| Article 7a | |
| Sectoral action plans | |
| 1. The Commission shall establish the sectoral action plans referred to in this Regulation. | |
| Those plans shall: | |
| a) set out, for each relevant industrial sector and value chain, a coherent strategy and clear objectives — including, for example, the recovery of market share, job creation, and the reduction of strategic dependencies — and implementation pathways aimed at strengthening the Union’s industrial capacity, resilience and decarbonisation in line with the Union’s climate and environmental objectives; | |
| b) identify the main challenges and bottlenecks affecting the development of the sector, including those related to research and innovation, investment including in production capacity and related to ports infrastructures, supply chains, skills, regulatory barriers, trade dynamics and propose appropriate solutions to address them; | |
| c) ensure the coordinated mobilisation of relevant Union instruments, in particular those under this legislation, the Clean Industrial Deal, state aids rules, trade defence instruments; | |
| d) adapt the tools established under this Regulation to the specific needs of each sector and value chain, including through the use of existing delegated powers, where appropriate. | |
| 2. The preparation and implementation of the sectoral action plans shall not delay the application of the general provisions of this Regulation. |
Connections
The dossier, the decisions on this text and its other versions.
No connections found for this item.
Sources & citation
Where the facts on this page come from, and how to cite it.
- Data source
- Licensed CC BY 4.0.
- Retrieved
- 23 November 2026
Cite as
European Parliament (2026). “AMENDMENTS 1245 - 1513 - Draft report Proposal for a Regulation of the European Parliament and of the Council establishing a framework of measures for the acceleration of industrial capacity and decarbonisation in strategic sectors and amending Regulations (EU) 2018/1724, (EU) 2024/1735 and (EU) 2024/3110”. Text, 19 October 2026. docId CJ80-AM-796440. EU Parl Watch Research. https://news.eu-parl.st-solutions.dev/texts/CJ80-AM-796440 (retrieved 23 November 2026). Data: EP Open Data API: document record, https://data.europarl.europa.eu/api/v2/documents/CJ80-AM-796440 (CC BY 4.0).
BibTeX
@misc{epw-text-cj80-am-796440,
author = {{European Parliament}},
title = {{AMENDMENTS 1245 - 1513 - Draft report Proposal for a Regulation of the European Parliament and of the Council establishing a framework of measures for the acceleration of industrial capacity and decarbonisation in strategic sectors and amending Regulations (EU) 2018/1724, (EU) 2024/1735 and (EU) 2024/3110}},
year = {2026},
date = {2026-10-19},
howpublished = {\url{https://news.eu-parl.st-solutions.dev/texts/CJ80-AM-796440}},
url = {https://news.eu-parl.st-solutions.dev/texts/CJ80-AM-796440},